Wednesday, January 1, 2020

Stopping one SAPH


  • Reduce Load to 300MW
  • Slowly close flue gas outlet damper (2 in no. )for APH which has to be stopped
  • Adjust other PAPH/SAPH flue gas outlet damper
  • Close flue gas inlet damper
  • Close SCAPH inlet , outlet & bypass damper. During Closing , Observe Air Flow.
  • Close SAPH air outlet damper (2 in no.)
  • Stop the SAPH motor once flue gas inlet temperature reduced below 150deg C
  • Close Air motor main isolating valve & bypass isolating valve

LIGHT UP CHECK POINTS



BEFORE LIGHT UP ACTIVITIES
BOILER SIDE
  • MAN ,MATERIAL REMOVED AND BOILER IS READY FOR LIGHT UP.

Water-chemistry: 500 MW

Recommended Parameter Values
1. Boiler Water – pH = 9.1-9.4
2. Boiler Water – Specific Conductivity < 20.0 μs/cm
3. Boiler Water – Silica < 100 ppb
4. Boiler Water - Phosphate = 1-2 ppm
5. Boiler Water - Chloride < 0.5 ppm

Check List (Light-Up)



Unit:
Date:

Switchyard Breaker arrangement: Rihand



Stage-I
GT#1  à 1-52  Main (GCB to Bus Bar-1) à 2-52 (Tie-GCB to bus Bar-2) à 3-52(IBT-1 i/c)
GT#2 à 7-52Main (GCB to Bus Bar-2) à 8-52((Tie-GCB to bus Bar-1)
Bus bar-1 à 4-52 (H1) à 5-52(Tie H1-S2) à 6-52(S2) à Bus Bar-2
Bus bar-2 à 10-52 (S1) à 11-52(Tie S1-H2) à 12-52(H2) à Bus Bar-1

Bus-1  ß13-52(Bus-coupler-1) à Bus-3
Bus-2  ß14-52(Bus-coupler-2) à Bus-4

Turbine Governing system



Key Points
Ø  Governing- Regulation of Turbine Speed under No Load and Varying Load
Ø  Others Works: CV Actuation/ Initial Run-up & Synchronization/ Load Variation to meet Grid Freq
Ø  500 MW KWU: Throttle Governed Machine
Ø  2 Governors , EHC and HG connected in Parallel: Only One at a time through Hyd Minimum slection
Ø  CVs Open according to Secondary oil Pressure
Ø  Between 100 MW  to 525 MW , Load variation done by HPCV throttling

Important Procedures



Vacuum Pulling : Procedure:
Ø  Close RH Vents, CRH, HRH UFT drains
Ø  Close Vacuum Breaker
Ø  Open 8.5 m steam Manual valve full Both (100%), Temp> 250 Deg ( Open
Ø  Start GSC Exhauster Fan
Ø  Start Both Vacuum pumps ( Casing Empty, Receiver tank Level adeq)
Ø  At -0.2 ksc charge steam gradually ( lower Controller from 50% à 0 %)
Ø  Build Vacuum upto -0.9 ksc

Hydrogen Purging



Ø  SLC AS SOP Off, SLC DC SOP Off, SLC H2 SOP Off
Ø  Suppy of DC SOP Off
Ø  Start one AC SOP ( DP=1.5 ksc)
Ø  Dew Point Air=<-10 Deg, clearance from Chemist
Ø  H2 (Isolated Position), CO2(Isolated Position), Air Inlet(Open), Casing vent ( Closed)
Ø  Fill and Pressurise upto 0.5 ksc

Cold start-up



Points to Remember
Ø  maximum of HP casing and HP shaft is less than 150°C(more than 5 days)
Ø  It requires soaking of Turbine at 360 rpm with steam(40ksc,360 Deg)
Ø  An upper limit of 200° C/hr. saturation temp gradients can be allowed, i.e. approximately the boiler pressure can be brought to 20 Kg/ Cm2 within an hour of cold start up
Ø  But actual temp gradient is limited by the thick walled Y piece provided in the main steam and HRH lines
Ø  maximum differential temp allowed between inner (98%) and mid wall temp (50%) is ±40°C
Ø  Start only two CC pumps in order to minimize flashing in down comers (and subsequent vibration) when the boiler water is in the range of 85° to 125° C

IBT Outage



Consequences on Stage-2 ( Station Transformer Tripped)
Ø  132 KV Switchyard dead results in tripping of -Station Transformers, Construction Transformer, Misc Transformer
Ø  All colony power( Lighting,Water supply) will get interrupted
Ø  Power Supply to DM Plant, HFO Pump house, PTCW Pump house, Offsite Board, ADPH,
Ø  Following Board will get dead:
§  OBA,OBB,OBC,OBD (11 KV station Board)
§  OCA,OCB (3.3 KV Station aux Board), ADPH MCC, CHP Transformers
§  DMPT, CWST, WTPT,BTST,ODA,ODB(Station Service), ODC(FW Pump House),ODD ( Offsite ): 3.3 KV
§  OQA,OQB(St. Serv),3SA,4SA(Air Washer MCC),3TA,4TA(Unit Ventilation MCC),OTA(HVAC ) : 415 V
§  OSA(SW MCC), OTB(Serv Bldg Ventilation MCC), FOPH : 415 V

Main Equipments Tripped


Instrument Air supply Failure



Reasons of  Failure:
Ø  Failure of control supply of  compressor
Ø  Loss of Cooling Water (SG ECW Pump Trip)
Ø  Massive leakage in  IA supply Header
Ø  One Unit Under Overhaul. Unit Aux Board/ Station Aux board  got Tripped of that Unit
Ø  Total Black Out of any stage

DG Load Trial and Regular checks



Requirements:
1
Inform & Ensure availability of TMD/EMD/C&I

2
SG/TG/BOP source-2 AC Power Supply Interruption. Inform C&I for Standby chargers

3
Ensure DG Set Tank Oil Level Adequate

4
Evacuate and Isolate Boiler Passenger, Service Building Lift and Isolate. Inform EMD(temporary supply )

5
Arrange 3 Walky Talky : 1-CR 2-DG board 3-DG Set room

6
Note Down Initial Parameters of DG Set

Furnace Air Tightness Test



Ø  Scope- Boiler Furnace, Air and FG Duct upto ID Fan Inlet
Ø  Why- To test Tightness of Furnace wrt Environment not for Strength
Ø  Ensure- All PTWs of BMD( PP, Rotary, Mills, Ash handling) cancelled and Clearance Available

Emergency Instructions:220 V DC Failure



220 V DC Failure
Unit condition
Ø  DCDB section-1 & 2 under voltage alarm in LVS-5
Ø  All HT/LT Breakers Indication Becomes Bad
Ø  Boiler will Trip on MFT ( after 2 Sec)
Ø  Turbine will Trip on MFT
Ø  Generator will not Trip as GCB Protection will not act
Ø  Generator will run as Synchronous Motor

Start-Up After 8 Hours of Shutdown ( Hot start-UP)



Unit condition
1
At least 2 BCW pump in Serrvice


2
Both SAPH and PAPH Running


3
Turbine : On Barring (AOP,JOP,SOP, HPCF  in service)


4
Generator: PW system, Seal Oil system, Gas system


5
Condenser Pass : Both Charged


6
PAC & IAC : 1 PAC & 2 IAC in Service


7
CEP & Make-up :  1 CEP with H/W Make-up on auto

Tripping on Boiler Tube Leakage


Wednesday, December 11, 2019

Unit Start Up Procedure 500 MW

Turbine and TDBFP Overspeed & Oil Injection Test Procedure


Oil Injection of Main Turbine:
  • Press Test Valve
  • Turn Test Hand-wheel Anticlockwise slowly ( to develop Test Oil)
  • Note Turbine Speed, Test Oil Pressure, Primary Oil Pressure when Bolts Operate(Aux Trip Oil becomes 0)
  • Turn Test Hand-wheel Clockwise slowly (Test Oil pressure becomes 0)

Thursday, December 13, 2018

Volumetric Vs Gravimetric Mode : Feeder

Volumetrric Vs Gravimetric Mode : Feeder


  • Coal properties constantly vary due to sizing differences and the adverse impact of moisture. These affect heating value, flow characteristics and density.The resultant density changes are measured by the Gravimetric Feeder. 
  •  The gravimetric feeder compensates for the variation in bulk density and feeds a fixed weight of coal in response to a boiler fuel demand
  •  This ability to accurately weigh the coal provides significant improvement over volumetric types in terms of matching the fuel delivered by the feeder to the actual process energy required on coal fired units. 
Benefits of Gravimetric Feeder


  • Fuel Savings through Improved Boiler Efficiency
  • Improved Combustion Efficiency/LOI
  • Less Slagging and Fouling, leading to Less Corrosion
  • Less NOx through Better Control of Excess Air
  • Stability and Improved Response of Combustion Controls
  • Improved Pulverizer/Cyclone/Combustor Performance
  • Reduced Safety Concerns

How It Works : Gravimetric Mode

  • Gravimetric feeder weighs material on a belt between two fixed points (span) precisely located in the feeder body.
  • A roller, located midway in the span and supported at each end by precision load cells, supports half the weight on the span
  • The load cells generate an electrical signal directly proportional to the weight supported. 
  •  The microprocessor takes samples of the output of each load cell many times a second. 
  • If the load cell outputs are within the expected range, they are added to obtain total weight per unit of belt length. 
  • Belt speed is determined by sampling the output of a tachometer attached to the motor shaft, multiplied by a calibration factor to convert it into a belt speed signal
  • The microprocessor multiplies the speed and weight signal for the feeder rate of fuel output.
  • Finally, the microprocessor matches the feeder output to the output required by the boiler control, by adjusting the feeder motor speed.
  • Feeders provide an accuracy of +/- ½ of one percent of totalized weight when calibrated and maintained

Volumetric feeding

  • Volumetric feeder is Open-loop device

  • Volumetric mode is set-speed constant , choke-fed or flooded infeed of a particulate solid and it feeds by volume only.
  • Feed must have consistent bulk density
  • As there is no information on  feedback of feeder ouput and drive control system

Selective Non-Catalytic Reduction | SNCR | NOx Emission control | Therma...