Start-Up After 8 Hours of Shutdown ( Hot start-UP)
Unit condition
1
|
At least 2 BCW pump in Serrvice
|
||
2
|
Both SAPH and PAPH Running
|
||
3
|
Turbine : On Barring
(AOP,JOP,SOP, HPCF in service)
|
||
4
|
Generator: PW system, Seal Oil
system, Gas system
|
||
5
|
Condenser Pass : Both Charged
|
||
6
|
PAC & IAC : 1 PAC & 2
IAC in Service
|
||
7
|
|||
8
|
PRDS : 13.5
ksc , Temp>260 Deg
|
Line-up from other units
|
|
9
|
ESP : Ready (Fields, Rapcon,
Heaters etc)
|
||
10
|
EAST Panel : Ready
|
||
11
|
LP & HP dosing system :
Ready
|
||
12
|
Bottom & Seal Trough : Lined
-Up
|
||
13
|
Evacuation system : Lined -Up /
charged (Pulled)
|
||
14
|
GRP Panel & Excitation:
Ready
|
||
15
|
Boiler Drum Pr=75 ksc, Ms
Temp=415-430 eg
|
BSVs Closed
|
|
16
|
LDO & Atomizing system :
Ready
|
LDO=16 ksc, Atomizing
Steam=6 ksc
|
Sequence
00'
|
Drum
Pr=75 ksc
|
Take
4 guns in AB elevation
|
Start
APH soot Blowing prior to firing
|
|
MST:
415-430
|
Open
Drain Before BSVs
|
|||
Open
BSV IBvs
|
MS
strainer drain to SDFT, UFT, CRH drain pot,
Open
|
|||
Open
BSvs
|
||||
Open
Warm-up Of HPBP and then HPBP and LPBP
|
HRH
Pr=2 ksc, Close CRH Drain pot
|
|||
Start
PA fan & seal air fans
|
Ensure
FG & air Damper of PAPH Open Prior PA Fans
|
|||
Line-Up
Milling system
|
Open CAG/CAD of at least 3 mills before PA Fan
start
|
|||
40'
|
MS=
85/485
|
Take
1st Mill
|
Make
Ready SH/RH spray
|
|
HR=12/440
|
Charge
ESP fields
|
Ensure
Ash Handling System Ready
|
||
Cut
in 2nd Mill
|
Peg
Deaerator with CRH (Pr=2 ksc)
|
|||
Reset
turbine
|
Bring
Starting Device to 0, Put TG LO TCV on auto-45 Deg
|
|||
50'
|
MS=85/500
|
Open
Turbine SGC seq/Switch ON/Select Start-up
|
105-Starting
Device (42 %) 109-
Tracking Device ON
|
|
HR=12/450
|
Raise
Starting Device to 100% once ESVs Opened
|
110-Speeder
Gear goes 100 %(If LT100%)
|
||
Bypass
flow BLI = 360 TPH
|
Hold
for 5 minutes at 360 rpm
|
112-
Turbine Speed 360 rpm command
|
||
52'
|
Raise
Turbine speed to 3000 rpm
|
116-Turbine
speed 3000 rpm command
|
||
(Rate
of Acceleration b/w 600-850 rpm2)
|
(OFF
: Turning gear=240 rpm, JOP=540 rpm )
|
|||
Switch
Off ATRS Program (After 116)
|
Monitor-Bearing
Temp/Pedestal-shaft Vibration ,TSI
|
|||
56'
|
Put
AVR on auto
|
Ensure
AOP: Off
|
||
Close
Field Breaker
|
Check
starting GT cooling Fans
|
|||
Select
GCB from ECP, put sync-ON
|
||||
Select
Auto-synchronizer made ON
|
Load
Ref=50 MW . Pr Max=75 MW
|
|||
Synchronize
Generator with Grid
|
Speed
set point raised by 8rpm and 20 MW load will come
|
|||
Raise
speed SP by small pulse
|
||||
Put
HPBP in Auto with increased SP
|
||||
60'
|
Load=60 MW
|
Cut
in LPH-2,3
|
Change-Over
of ST to UT
|
|
MS=85
/500
|
Cutout
Heating system from PRDS to Deaerator
|
|||
HRH=16/470
|
Raise
D/A Pr from 2 ksc to 4ksc
|
|||
Cut
in all Controllers
|
||||
65'
|
Load=150 MW
|
Charge
PRDS from CRH
|
||
MS=100/500
|
Cut
in HP Heaters
|
|||
HRH=20/480
|
Start
2nd CEP, 1st TDBFP at Load=170
MW
|
|||
BLI=
600 TPH
|
Control
MS/HRH Temp by spray (If Required)
|
|||
Trim
Dev : Off
|
Change
D/A Pegging from CRH to Extraction
|
|||
Cut
in 3rd Mill
|
||||
70'
|
Load=230 MW
|
Cut
in 4th Mill
|
||
MS=120/500
|
Cut
off Oil Support
|
Ensure
Healthiness of Scanners
|
||
HRH=25/495
|
Cut
in 5th Mill
|
|||
BLI=820
TPH
|
Start
2nd TDBFP and Switch off MDBFP
|
|||
Cut
in 6th Mill
|
||||
86'
|
Load=500 MW
|
Ensure
all controllers in auto
|
||
MS=170/500
|
||||
HRH=40/500
|
||||
BLI=1620
TPH
|
||||
135'
|
Load=500 MW
|
MS=170/535, HRH=45/535
|
Comments