Requirements:
1
Inform & Ensure availability of TMD/EMD/C&I

2
SG/TG/BOP source-2 AC Power Supply Interruption. Inform C&I for Standby chargers

3
Ensure DG Set Tank Oil Level Adequate

4
Evacuate and Isolate Boiler Passenger, Service Building Lift and Isolate. Inform EMD(temporary supply )

5
Arrange 3 Walky Talky : 1-CR 2-DG board 3-DG Set room

6
Note Down Initial Parameters of DG Set


Status of Unit:
1
TG on Barring

2
Generator Depressurized(H2/CO2 Purged out)

3
Seal Oil system in Service

4
All Drives in DG Bus in available condition( Plan within 1-2 days of Unit shut down)

5
DG Board charged from Normal Incomer Breaker from Unit Service Board


Sequence:
Ø  Start all drives on DG Bus from other standby source(other board)
Ex- SOP-2 to Sop-1, FD/ID/PA Lop-2 to LOP-1
Ø  Start Main DG set & Note Down: Volatge, RPM, Tank Level, LO Pr/Temp, Battery Voltage
Ø  Trip Normal Incomer from USS and Close DG set Incoming breaker to charge DG Bus
Ø  Start Loading Drives by starting them which are on DG Bus
Ø  Continue Test run fro ½ -1 Hour.
Normalisation:
Ø  Start all drives on DG Bus from other standby source(other board)
Ø  Trip DG Set Incoming Breaker  and Close Normal Incomer From USS
Ø  Switch Off DG Set
Regular checks:
Ø  DG Set Fuel Tank Level Normal
Ø  DG Set engine Oil Level Normal
Ø  Battery charger OK
Ø  Engine Coolant level is OK
Ø  DG Set Incomers to DG Bus Healthy