Thermal Power Plant Operation Information guide. Please find here the Stand ard Operating Procedures, Instructions to operate various capacity Thermal power plants in India. This is as per my experience and any abnormality found please refer other sources. Thank you.
Friday, September 5, 2025
DSI SOP
STANDARD OPERATING
PRACTICE (DSI)
NTPC DADRI
STAGE I – 4X210 MW
DRY SORBENT INJECTION SYSTEM
DSI EQUIPMENTS
1. Instrument air compressor
2. Viper mill
3. Oil pump viper mill
4. Blower ( injection and unloading )
5. Dehumidifier ( injection and unloading )
6. Heat Exchanger ( injection and unloading )
7. SBC silo
8. Weigh hopper
9. Rotary air lock ( RAL )( Injection and unloading )
10. Rotary vane feeder ( RVF )
11. Jumbo bag hopper
12. Splitter
Dadri-1: Mill c/o guidelines
Mill starting procedure :
·
Clearance from local
operator is to be recorded before starting mill.
·
Ensure feeder coal on belt
is established.
·
Ensure ignition permit is available.
·
Open bunker outlet &
feeder inlet gate.
·
Start Mill LOP and observe
lub oil pressure , temperature and flow.
·
Open CAG ( CADshould be
closed), monitor PA header pressure.
·
Start Mill and monitor its
current (60-65 Amp normal current).
·
Open feeder seal air valve
& feeder outletgate.
·
Open HAG,( HAD should be
closed), monitor PA header pressure.
·
Observe boiler flame
intensity during mill operation.
Dadri: biomass Operating Procedure
1)
Mill Operating Parameters and
Operation procedure: -
Ø
Maintain
Mill outlet temperature-> 55 C
Ø
Mill
inlet temperature -> not more than 180 C
Ø
Observe
all 4 coal pipe temperature of Mills with biomass regularly. In case of any
deviation from rest of the pipes (any abrupt rise or fall), stop the mill and
give PTW for inspection.
Ø
Pre
start and post shutdown purging of mill is mandatory.
Ø
Continuous
monitoring of mill parameters most importantly mills inlet air temperature, mill
outlet temperature, mill current and mill DP.
Ø
Mill
inlet temperature should not be more than 180 C in any case
Ø
Mill
reject system to be kept under observation continuously
Ø
Operator
should be deployed at local for monitoring in wake of fire hazard.
Ø
In
case of fire, mill should be tripped and steam inerting should be done
immediately by opening steam interting motorized valve, keeping watch on
furnace pressure. Fire tender may also
be used if required.
Ø
Clinkering
and slagging tendency to be observed from local as well as from rise in SH zone
FG temperature. Soot blowing and LRSB to be done accordingly.
Dadri-1: Boiler Safety valve float data
BOILER SAFETY VALVES FLOATING PROTOCOL.
UNIT DATE:
|
S.NO. |
VALVE NO. |
DESIGN PR.(KSC) |
ACTUAL PR.(KSC) |
||
|
|
|
OPERATING PR. |
RESET PR. |
OPERATING PR. |
RESET PR. |
|
1 |
SV-1 |
176 |
169.3 |
|
|
|
2 |
SV-2 |
179.9 |
170.9 |
|
|
|
3 |
SV-3 |
181.7 |
172.6 |
|
|
|
4 |
SV-4 |
163 |
158.1 |
|
|
|
5 |
SV-5(ERV-1) |
161.4 |
158 |
|
|
|
6 |
SV-6(ERV-2) |
161.4 |
158 |
|
|
|
7 |
SV-7 |
49 |
46.6 |
|
|
|
8 |
SV-8 |
46.3 |
44.0 |
|
|
|
9 |
SV-9 |
46.66 |
44 |
|
|
|
10 |
SV-10 |
48.42 |
46.0 |
|
|
|
11 |
SV-11(ERV-3) |
45.8 |
44.9 |
|
|
|
12 |
SV-12(ERV-4) |
45.8 |
44.9 |
|
|
Dadri-1: DOR
DOR OF HT/LT MOTORS
CONVENTION:
DOR TAKEN
FROM NDE SIDE OF MOTOR
C: CLOCKWISE A: ANTI CLOCKWISE
HT MOTORS
|
ID A/B |
A |
MILL
A/B/C/D/E/F |
C |
PA A |
C |
|
FD A /B |
A |
ECW A/B/C |
C |
PA B |
A |
|
CEP A/B |
C |
BFP
A//B/C |
C |
CW A/B |
A |
|
|
|
|
|
TAC A/B |
C |
LT MOTORS
1. BOILER
|
ID LOP-A/B |
C |
FEEDER MAIN MTR |
C |
|
ID AOP A/B |
C |
FEEDER
COC MTR |
C |
|
FD LOP A/B |
C |
SCANNER
FAN AC |
C |
|
PA LOP
A/B |
C |
SCANNER
FAN DC |
C |
|
PA AOP
A/B |
C |
SEAL AIR
FAN A/B |
A |
|
MILL LOPA/B |
C |
APH A
MAIN MTR |
A |
|
APH GB
LOP A/B |
C |
APH A S/B
MTR |
A |
|
APH SB
LOP A/B |
C |
APH B
MAIN MTR |
C |
|
|
|
APH B S/B
MTR |
C |
Dadri-1: after Shutdown Activities
ACTIVITIES AFTER UNIT SHUTDOWN (SHORT SHUTDOWN 8Hrs TO
72 Hrs) STAGE-1
1. After closing MS-1 & 2, isolate electrical supply.
2. Before killing Vacuum,
a) open MS & HRH line drains to IBD
b) close all drains to flash box and condenser
c) Open HPBP line drain lines at 8.5 M.
d) MS line is depressurized.
Dadri -1: Reserve Shutdown Procedure
PROCEDURE FOR
RESERVE SHUT DOWN OF STAGE-1 UNITS
PREPARATIONS
1. Open the seal steam drain v/v, MAL-81 and ensure the temp. above 230 deg before seal steam controller,
2. Put the oil guns of AB & CD elevation in scavenge.
3. Open the manual isolating v/v of CBD line at 19 M & 3.5 M.
4. Get the reqd. protections bypassed by C&I engr.
5. Close the Aux. PRDS if in service. (Close As-11, AS-12).
6. Close HT hdr isolating valve at Deaerator floor.
7. Inform CHP , AHP & Switchyard c/r regarding shut down plan.
8. Note down the HFO counter reading.
Dadri-1: Pre-lightup checklist
Light up preparation Checklist
BOILER SIDE
1. Deployment of CISF person(IOM & information to CISF)(one person for Blr & Tur. Each)
2. Ensure opening of manual isolating v/v of following
a. CBD
b. IBD
c. MS-203 MS-204
d. HRH-203,HRH-204
e. IBD side drains of MS & HRH LINE
f. Boiler vents
g. SH vents
h. SH Hdr. drains
i. Isolating valves of ERV’s
j. Boiler startup vent
Wednesday, September 3, 2025
Wednesday, February 28, 2024
Tuesday, January 30, 2024
Dadri stage-1 Light up Preparation
LIST OF ACTIVITIES AFTER UNIT LIGHT UP
(WARM/HOT START UP AFTER TUBE LEAKAGE)
Dadri stage-1 after Light up checklist
LIST OF ACTIVITIES AFTER UNIT LIGHT UP
(WARM/HOT START UP AFTER TUBE LEAKAGE)
Dadri stage-1 After shutdown Work
ACTIVITIES AFTER UNIT SHUTDOWN (SHORT SHUTDOWN 8Hrs TO
72 Hrs) STAGE-1
1. After closing MS-1 & 2, isolate electrical supply.
Dadri Stage-1 Start up Write-up
SOP to avoid unit
disturbance/tripping during litup/turbine rolling/unit synchronization
1. APH oil carryover probe to be checked
hourly during light up. Oil gun having poor flame to be removed. APH soot
blowing to continue till oil guns in
service. CBD to be opened after boiler litup and closed as per chemistry
clearance. SCAPH charging &Dearator heating / pegging to be done .
Condensate dumping to be done.
Dadri stage-1 Turbine Interlock & Protection
Dadri stage-1 Turbine Interlock & Protection
- Lub Oil Pr: Alarm=2.0 ksc. Trip=1.88 ksc Effect: Turbine Trips, Barring gear Protection Close,Vacuum Breaker Opens
Friday, October 13, 2023
Dadri U-1 functional Loocation /Job Card Help
Functional loc. 1011-S1U01 Valid From 20.08.17
Description STAGE-1 UNIT-1
Wednesday, July 12, 2023
Friday, May 26, 2023
Dadri stage-1 Reserve Shut down Procedure
PROCEDURE FOR RESERVE SHUT DOWN OF STAGE-1 UNITS
PREPARATIONS
Dadri stage-1 : ST-1, ST-2 Both tripping
In case of both station transformer tripping following disturbance will be observed
Tuesday, October 11, 2022
Thursday, July 30, 2020
Work Instructions
|
1
|
At
least 2 BCW pump in Serrvice
|
|
|
|
2
|
Both
SAPH and PAPH Running |
|
|
|
3
|
Turbine
: On Barring (AOP,JOP,SOP, HPCF in service) |
|
|
|
4
|
Generator:
PW system, Seal Oil system, Gas system |
Monday, June 1, 2020
SCED Features
- NLDC has opened a separate bank account called ‘National Pool Account (SCED)’. All payments to/from the generators and to the Discoms on account of SCED flow to/from the said National Pool Account (SCED)
Power Terminology
- 100MW for 24 Hrs = 2.4 MU (Million Units)
- Ancillary services refer to functions that help grid operators maintain a reliable electricity system.
- Ancillary services maintain the proper flow and direction of electricity, address imbalances between supply and demand, and help the system recover after a power system event
RH Metal Temp Optimization
- Causes of Rh Tube Fail:
(b) UNEVEN TEMPERATURE DISTRIBUTION ACROSS THE BOILER
Dry Ash system : 500 MW
- Ash is oxidised form of the mineral matters present in coal
- Typical ash composition : SiO2, Al2O3, Fe2O3, CaO, MgO etc
- Coal with more SiO2 & Al2O3, Ash MP > 1400ºC
Shut-Down Procedure: 500 MW (Planned Shutdown)
- Reduce load from 500 MW to 400 MW
- Gradualy Reduce Pr SP from 170 ksc to 130 ksc, Load is still 400 MW
- Take unit of TFM
-
HP & LP Bypass Operation and Protection Purpose Boiler operation independent of the turbine Minimum steam flow through SH &...
-
Generator Air Tightness Test Period Of Test= 24 Hrs without a Break Air Pressure Drop (Allowed in 24 Hrs) : <=0.15 ksc Air Test Pre...