LIST OF ACTIVITIES AFTER UNIT LIGHT UP

(WARM/HOT START UP AFTER TUBE LEAKAGE)

 

Sl.No.

ACTIVITIES

REMARKS

1.     

After purging, light up the boiler with ldo guns

 

2.     

Start aph soot blowing from aux. prds

 

3.     

Change over ldo to hfo guns (ensure hfo temp is around 110 0C at boiler front)

 

4.     

Line up condenser vacuum pulling system & start vacuum pulling

 

5.     

Maintain drum level within limit (ensure line up of ibd.cbd and ebd valves.

 

6.     

Close boiler air vents at 3 ksc

 

7.     

Charge ms line at 8 ksc (ensure opening of mal ms. Hrh strainer and hp bypass up stream drains)

 

8.     

Open hp bypass spray manual isolating valve

 

9.     

Close sh header drains

 

10.   

Take coal mill in service (if required) to raise ms temp 30 0C above hp shaft mid temp for hot/warm rolling

 

11.   

After coal firing, charge esp fields

 

12.   

Line up sh/ rh spray system and try to maintain zero spray till synchronising   of m/c

 

13.   

Switch on atrs programme for turbine rolling

 

14.   

Ensure closing of gate v/v gearing at 250 rpm

 

15.   

Ensure stopping of job at 250 rpm

 

16.   

Soak turbine at 540 rpm for 20 minutes (if required)

 

17.   

Inform sw. yard engr to close bus and line isolator of generator breaker

 

18.   

Charge stator water, seal oil & hydrogen coolers at 540 rpm

 

19.   

Raise turbine speed to 3000 rpm thro atrs (monitor turbine lub oil pressure, duplex filter choking and tg vibrations)

 

20.   

Switch off atrs programme at 3000 rpm

 

21.   

Close field breaker at 3000 rpm and build up generator voltage around 16.5 kv

 

22.   

Set load limiter at 50mw, load set point at 30mw and load gradient 20 mw/min

 

23.   

Switch on the synchronous scope and match synchronising  parameters

 

24.   

Synchronise the machine when synchronous scope gives green signal

 

25.   

Charge lp heaters and d/a extraction

 

26.   

Put turbine drains slc on and close ms and hrh strainer

 

27.   

At 30 mw, change over 6.6kv bus from statin to uat

 

28.   

Raise fuel firing and generator load as per tse margin

 

29.   

Charge hp heaters at 120mw

 

30.   

Put machine in cmc mode after achieving full load

 

31.   

 

 

 

 