Dadri Stage-1 Start up Write-up
SOP to avoid unit
disturbance/tripping during litup/turbine rolling/unit synchronization
1. APH oil carryover probe to be checked
hourly during light up. Oil gun having poor flame to be removed. APH soot
blowing to continue till oil guns in
service. CBD to be opened after boiler litup and closed as per chemistry
clearance. SCAPH charging &Dearator heating / pegging to be done .
Condensate dumping to be done.
2. Fire personnel should be called
before lit up.
3. Economizer recirculation valve kept
open till load raised more than 10%.
4. Raise PA header pressure slowly to avoid
rupturing of NMEJ.
5. APH flue gas to be charged slowly
after air charging.
6. Both TDBFP should be rolled before
turbine rolling.
7. Turbine should be rolled as per X1-X7
rolling criteria.
8. MS silica to be recorded before
turbine rolling (Inform Chemistry to
check sample for checking silica after HP/LP bypass charging).
9. HP/IP trimming device kept ON
(normal).
10. Turbine speed/load signal should be
healthy.
11. Keep all MAL drains open.
12. DCLOP & DC SOP trial should be
taken before rolling.
13. CRH NRV status (ON/OFF) should be
healthy before rolling.
14. SLC of lube oil system, JOP, barring
gear valve, HPCF system, stator water& seal oil system kept ON.
15. Monitor TG Lube oil filter choking
before rolling.
16. TG lubeoil ,HPCF, H2 cooler & PSW
cooler controller kept in auto.
17. All standby equipment to be kept in
auto.
18. MS / RH pressure to maintained as per
casing temperature & type of start up.
19. All TG parameters to be seen before
rolling of turbine including MAL drain temperatures.
20. Turbine throttle pressure to set at zero
before turbine rolling
21. TSE margin to be monitored and have
sufficient margin during rolling & unit loading.
22. Turbine stop valve gagging should be
removed and EHTC oil supply kept normal. Keep speeder gear 100%.
23. TG luboil temperature to be maintained at 45 degree.
24. TSI parameters & TG bearing
temperatures to be monitored.
25. TG gland seal pressure (200-250 mmwc)
& temperature (> 280 degree) to be maintained.
26. DN/dt to be maintained close to
600rpm/min2during rolling.
27. PR (max ) to be set at 10% of load
and raise after unit synchronization andon seeing turbine protection inputs.
28. Monitor closing/stopping of barring gear
valve/JOP/AOP as per logic.
29. GT oil pump running status to be confirmedfrom
local after excitation made ON.
30. HPT exhaust temperature to be
monitored at 3000 rpm.
31. GRP relay to reset at 3000 rpm. GCB
isolator to be closed and kept in remote.Switchyard person to inform before
rolling & synchronization.
32. Unit synchronization should be done
through auto synchronizer.
33. Block load(20 Mw for stage-I & 50
MW for stage-2) to be raised as quickly as possible. Unit control to be shifted
from speed control to load control and speed reference should start tracking
actual speed .
34. Ensure GCB ON status should appear
after unit synchronization.
35. HP/IP control valve status to be monitored.
36. HP/IP top bottom DT to be monitored.
37. Try to keep IPCV full open during
load raising
38. Load to be restrict less than 70 MW ,
If turbine extended protection value are in tripping range.
39. MAL drains to be closed as per ATRS
criteria.
40. HP/LP bypass to be kept in manual
after turbine rolling and valve to be closedafter watching change in boiler
pressure to avoid load hunting at part load during warm rolling. Bypass tobe
kept in auto after load stabilization.
41. Generator seal oil temperature to be
monitored.
42. Generator temperatures to be
monitored during load raising
43. Cold gas ,stator water, & exciter air temperature to be
monitored.
44. Stator water conductivity to be monitored.
45. LLD level to be monitored during
startup.
46. Generator voltage to be maintained
during load raising.
47. H2 pressure & seal oil DP to be
monitored
48. Condenser vacuum to be monitored
during load raising.
49. Turbine extraction to be charged
after proper draining.LPH/Deaerator extraction to be charged below 100 MW &
HPH extraction at 150 MW.
50. Boiler pressure to be maintained as
per load.
51. Feed water low range to high range
changeover to be done after keeping DP zero.
52. Maintain hotwell, dearator, drum
level, MS/RH steam temperature and drum pressure during load raising.
53. Bunker outlet /Feeder inlet gate
should be open.
54. Oil gun to be removed afterboiler
healthy flame.
55. All ESP flue gas gates to be opened after 02 mills in service. (since lit up is done
with ESP two pass charged).
56. ESP fields to be charged after oil
gun removal.
57. Coal feeding to be done slowly to
avoid boiler pressure & temperature rise abruptly.
58. Maintain furnace pressure, PA header
pressure, O2 % during load raising.
59. Maintenance personnel should be
present during load raising/unit stabilization
60. Unit protection to be normalized as
early as possible.
61. Observe MOT/HPCF/TDBFP oil levels
Comments