Check List (Light-Up)

Unit: Date:

Switchyard Breaker arrangement: Rihand

Stage-I GT#1  à 1-52   Main (GCB to Bus Bar-1) à 2-52 (Tie-GCB to bus Bar-2) à 3-52(IBT-1 i/c) GT#2 à 7-52Main (GCB to Bus Bar-2) à 8-52((Tie-GCB to bus Bar-1) Bus bar-1 à 4-52 (H1) à 5-52(Tie H1-S2) à 6-52(S2) à Bus Bar-2 Bus bar-2 à 10-52 (S1) à 11-52(Tie S1-H2) à 12-52(H2) à Bus Bar-1 Bus-1   ß 13-52(Bus-coupler-1) à Bus-3 Bus-2   ß 14-52(Bus-coupler-2) à Bus-4

Turbine Governing system

Key Points Ø   Governing- Regulation of Turbine Speed under No Load and Varying Load Ø   Others Works: CV Actuation/ Initial Run-up & Synchronization/ Load Variation to meet Grid Freq Ø   500 MW KWU: Throttle Governed Machine Ø   2 Governors , EHC and HG connected in Parallel: Only One at a time through Hyd Minimum slection Ø   CVs Open according to Secondary oil Pressure Ø   Between 100 MW   to 525 MW , Load variation done by HPCV throttling

Important Procedures

Vacuum Pulling : Procedure: Ø   Close RH Vents, CRH, HRH UFT drains Ø   Close Vacuum Breaker Ø   Open 8.5 m steam Manual valve full Both (100%), Temp> 250 Deg ( Open Ø   Start GSC Exhauster Fan Ø   Start Both Vacuum pumps ( Casing Empty, Receiver tank Level adeq) Ø   At -0.2 ksc charge steam gradually ( lower Controller from 50% à 0 %) Ø   Build Vacuum upto -0.9 ksc

Hydrogen Purging

Ø   SLC AS SOP Off, SLC DC SOP Off, SLC H2 SOP Off Ø   Suppy of DC SOP Off Ø   Start one AC SOP ( DP=1.5 ksc) Ø   Dew Point Air=<-10 Deg, clearance from Chemist Ø   H2 (Isolated Position), CO2(Isolated Position), Air Inlet(Open), Casing vent ( Closed) Ø   Fill and Pressurise upto 0.5 ksc

Cold start-up

Points to Remember Ø   maximum of HP casing and HP shaft is less than 150 ° C(more than 5 days) Ø   It requires soaking of Turbine at 360 rpm with steam(40ksc,360 Deg) Ø   An upper limit of 200 ° C/hr. saturation temp gradients can be allowed , i.e. approximately the boiler pressure can be brought to 20 Kg/ Cm 2 within an hour of cold start up Ø   But actual temp gradient is limited by the thick walled Y piece provided in the main steam and HRH lines Ø   maximum differential temp allowed between inner (98%) and mid wall temp (50%) is ±40 ° C Ø   Start only two CC pumps in order to minimize flashing in down comers (and subsequent vibration) when the boiler water is in the range of 85 ° to 125 ° C

IBT Outage

Consequences on Stage-2 ( Station Transformer Tripped) Ø   132 KV Switchyard dead results in tripping of -Station Transformers, Construction Transformer, Misc Transformer Ø   All colony power( Lighting,Water supply) will get interrupted Ø   Power Supply to DM Plant, HFO Pump house, PTCW Pump house, Offsite Board, ADPH, Ø   Following Board will get dead : §   OBA,OBB,OBC,OBD (11 KV station Board) §   OCA,OCB (3.3 KV Station aux Board), ADPH MCC, CHP Transformers §   DMPT, CWST, WTPT,BTST,ODA,ODB(Station Service), ODC(FW Pump House),ODD ( Offsite ): 3.3 KV §   OQA,OQB(St. Serv),3SA,4SA(Air Washer MCC),3TA,4TA(Unit Ventilation MCC),OTA(HVAC ) : 415 V §   OSA(SW MCC), OTB(Serv Bldg Ventilation MCC), FOPH : 415 V

Main Equipments Tripped

Instrument Air supply Failure

Reasons of   Failure: Ø   Failure of control supply of   compressor Ø   Loss of Cooling Water (SG ECW Pump Trip) Ø   Massive leakage in   IA supply Header Ø   One Unit Under Overhaul. Unit Aux Board/ Station Aux board   got Tripped of that Unit Ø   Total Black Out of any stage

DG Load Trial and Regular checks

Requirements: 1 Inform & Ensure availability of TMD/EMD/C&I 2 SG/TG/BOP source-2 AC Power Supply Interruption. Inform C&I for Standby chargers 3 Ensure DG Set Tank Oil Level Adequate 4 Evacuate and Isolate Boiler Passenger, Service Building Lift and Isolate. Inform EMD(temporary supply ) 5 Arrange 3 Walky Talky : 1-CR 2-DG board 3-DG Set room 6 Note Down Initial Parameters of DG Set

Furnace Air Tightness Test

Ø   Scope - Boiler Furnace, Air and FG Duct upto ID Fan Inlet Ø   Why - To test Tightness of Furnace wrt Environment not for Strength Ø   Ensure- All PTWs of BMD( PP, Rotary, Mills, Ash handling) cancelled and Clearance Available

Emergency Instructions:220 V DC Failure

220 V DC Failure Unit condition Ø   DCDB section-1 & 2 under voltage alarm in LVS-5 Ø   All HT/LT Breakers Indication Becomes Bad Ø   Boiler will Trip on MFT ( after 2 Sec) Ø   Turbine will Trip on MFT Ø   Generator will not Trip as GCB Protection will not act Ø   Generator will run as Synchronous Motor

Start-Up After 8 Hours of Shutdown ( Hot start-UP)

Unit condition 1 At least 2 BCW pump in Serrvice 2 Both SAPH and PAPH Running 3 Turbine : On Barring (AOP,JOP,SOP, HPCF   in service) 4 Generator: PW system, Seal Oil system, Gas system 5 Condenser Pass : Both Charged 6 PAC & IAC : 1 PAC & 2 IAC in Service 7 CEP & Make-up :   1 CEP with H/W Make-up on auto

Tripping on Boiler Tube Leakage

Image

Mill reject system

Image

CERC Norms 2019 Vs 2014 : Changes

Image

TDBFP Rolling

Image

Beautiful Power Plant View from Top of Boiler at Night

Image

Sample Cooler

Image

Starting and Load Limiting Device

Image

Unit Start Up Procedure 500 MW

Image

Turbine and TDBFP Overspeed & Oil Injection Test Procedure

Oil Injection of Main Turbine: Press Test Valve Turn Test Hand-wheel Anticlockwise slowly ( to develop Test Oil) Note Turbine Speed, Test Oil Pressure, Primary Oil Pressure when Bolts Operate(Aux Trip Oil becomes 0) Turn Test Hand-wheel Clockwise slowly (Test Oil pressure becomes 0)

How to handle Station Black out In Power Plant ?

Image