Energy Tab
BHEL make 500 MW
Tuesday, February 27, 2024
Monday, January 29, 2024
Dadri stage-1 Light up Preparation
LIST OF ACTIVITIES AFTER UNIT LIGHT UP
(WARM/HOT START UP AFTER TUBE LEAKAGE)
Dadri stage-1 after Light up checklist
LIST OF ACTIVITIES AFTER UNIT LIGHT UP
(WARM/HOT START UP AFTER TUBE LEAKAGE)
Dadri stage-1 After shutdown Work
ACTIVITIES AFTER UNIT SHUTDOWN (SHORT SHUTDOWN 8Hrs TO
72 Hrs) STAGE-1
1. After closing MS-1 & 2, isolate electrical supply.
Dadri Stage-1 Start up Write-up
SOP to avoid unit
disturbance/tripping during litup/turbine rolling/unit synchronization
1. APH oil carryover probe to be checked
hourly during light up. Oil gun having poor flame to be removed. APH soot
blowing to continue till oil guns in
service. CBD to be opened after boiler litup and closed as per chemistry
clearance. SCAPH charging &Dearator heating / pegging to be done .
Condensate dumping to be done.
Dadri stage-1 Turbine Interlock & Protection
Dadri stage-1 Turbine Interlock & Protection
- Lub Oil Pr: Alarm=2.0 ksc. Trip=1.88 ksc Effect: Turbine Trips, Barring gear Protection Close,Vacuum Breaker Opens
Thursday, October 12, 2023
Dadri U-1 functional Loocation /Job Card Help
Functional loc. 1011-S1U01 Valid From 20.08.17
Description STAGE-1 UNIT-1
Tuesday, July 11, 2023
Thursday, May 25, 2023
Dadri stage-1 Reserve Shut down Procedure
PROCEDURE FOR RESERVE SHUT DOWN OF STAGE-1 UNITS
PREPARATIONS
Dadri stage-1 : ST-1, ST-2 Both tripping
In case of both station transformer tripping following disturbance will be observed
Monday, October 10, 2022
Wednesday, July 29, 2020
Work Instructions
1
|
At
least 2 BCW pump in Serrvice
|
|
|
2
|
Both
SAPH and PAPH Running |
|
|
3
|
Turbine
: On Barring (AOP,JOP,SOP, HPCF in service) |
|
|
4
|
Generator:
PW system, Seal Oil system, Gas system |
Monday, June 1, 2020
TDBFP LOP protection and Auto Start
SCED Features
- NLDC has opened a separate bank account called ‘National Pool Account (SCED)’. All payments to/from the generators and to the Discoms on account of SCED flow to/from the said National Pool Account (SCED)
Power Terminology
- 100MW for 24 Hrs = 2.4 MU (Million Units)
- Ancillary services refer to functions that help grid operators maintain a reliable electricity system.
- Ancillary services maintain the proper flow and direction of electricity, address imbalances between supply and demand, and help the system recover after a power system event
RH Metal Temp Optimization
- Causes of Rh Tube Fail:
(b) UNEVEN TEMPERATURE DISTRIBUTION ACROSS THE BOILER
Dry Ash system : 500 MW
- Ash is oxidised form of the mineral matters present in coal
- Typical ash composition : SiO2, Al2O3, Fe2O3, CaO, MgO etc
- Coal with more SiO2 & Al2O3, Ash MP > 1400ÂșC
Sunday, May 31, 2020
Shut-Down Procedure: 500 MW (Planned Shutdown)
- Reduce load from 500 MW to 400 MW
- Gradualy Reduce Pr SP from 170 ksc to 130 ksc, Load is still 400 MW
- Take unit of TFM
-
HP & LP Bypass Operation and Protection Purpose Boiler operation independent of the turbine Minimum steam flow through SH &...
-
Generator Air Tightness Test Period Of Test= 24 Hrs without a Break Air Pressure Drop (Allowed in 24 Hrs) : <=0.15 ksc Air Test Pre...