Energy Tab
BHEL make 500 MW
Tuesday, February 27, 2024
Monday, January 29, 2024
Dadri stage-1 Light up Preparation
LIST OF ACTIVITIES AFTER UNIT LIGHT UP
(WARM/HOT START UP AFTER TUBE LEAKAGE)
Dadri stage-1 after Light up checklist
LIST OF ACTIVITIES AFTER UNIT LIGHT UP
(WARM/HOT START UP AFTER TUBE LEAKAGE)
Dadri stage-1 After shutdown Work
ACTIVITIES AFTER UNIT SHUTDOWN (SHORT SHUTDOWN 8Hrs TO
72 Hrs) STAGE-1
1. After closing MS-1 & 2, isolate electrical supply.
Dadri Stage-1 Start up Write-up
SOP to avoid unit
disturbance/tripping during litup/turbine rolling/unit synchronization
1. APH oil carryover probe to be checked
hourly during light up. Oil gun having poor flame to be removed. APH soot
blowing to continue till oil guns in
service. CBD to be opened after boiler litup and closed as per chemistry
clearance. SCAPH charging &Dearator heating / pegging to be done .
Condensate dumping to be done.
Dadri stage-1 Turbine Interlock & Protection
Dadri stage-1 Turbine Interlock & Protection
- Lub Oil Pr: Alarm=2.0 ksc. Trip=1.88 ksc Effect: Turbine Trips, Barring gear Protection Close,Vacuum Breaker Opens
Thursday, October 12, 2023
Dadri U-1 functional Loocation /Job Card Help
Functional loc. 1011-S1U01 Valid From 20.08.17
Description STAGE-1 UNIT-1
Tuesday, July 11, 2023
Thursday, May 25, 2023
Dadri stage-1 Reserve Shut down Procedure
PROCEDURE FOR RESERVE SHUT DOWN OF STAGE-1 UNITS
PREPARATIONS
Dadri stage-1 : ST-1, ST-2 Both tripping
In case of both station transformer tripping following disturbance will be observed
Monday, October 10, 2022
Wednesday, July 29, 2020
Work Instructions
1
|
At
least 2 BCW pump in Serrvice
|
|
|
2
|
Both
SAPH and PAPH Running |
|
|
3
|
Turbine
: On Barring (AOP,JOP,SOP, HPCF in service) |
|
|
4
|
Generator:
PW system, Seal Oil system, Gas system |
Monday, June 1, 2020
TDBFP LOP protection and Auto Start
SCED Features
- NLDC has opened a separate bank account called ‘National Pool Account (SCED)’. All payments to/from the generators and to the Discoms on account of SCED flow to/from the said National Pool Account (SCED)
Power Terminology
- 100MW for 24 Hrs = 2.4 MU (Million Units)
- Ancillary services refer to functions that help grid operators maintain a reliable electricity system.
- Ancillary services maintain the proper flow and direction of electricity, address imbalances between supply and demand, and help the system recover after a power system event
RH Metal Temp Optimization
- Causes of Rh Tube Fail:
(b) UNEVEN TEMPERATURE DISTRIBUTION ACROSS THE BOILER
Dry Ash system : 500 MW
- Ash is oxidised form of the mineral matters present in coal
- Typical ash composition : SiO2, Al2O3, Fe2O3, CaO, MgO etc
- Coal with more SiO2 & Al2O3, Ash MP > 1400ºC
Sunday, May 31, 2020
Shut-Down Procedure: 500 MW (Planned Shutdown)
- Reduce load from 500 MW to 400 MW
- Gradualy Reduce Pr SP from 170 ksc to 130 ksc, Load is still 400 MW
- Take unit of TFM
Saturday, May 30, 2020
Thursday, May 21, 2020
Hydrogen Purging
1. The generator may be on barring gear or at standstill. Preferably be on barring speed of around 50-80rpm (without condenser vacuum).
At least 60 CO2 filled cylinders should be available in the unit where purging is to be done.
Arrangement for filling hot water on CO2 cylinder / lines (to avoid freezing) is to be ready.
Loss of Instrument Air
Anticipated Problems:
1. No oil burner can be taken in service. Oil guns, oil/steam valves will remain inoperative.
The igniter will not get advance.
Vacuum Pulling Process
1 Ensure permit cancellation on Vacuum pump/Flash Tank related MOV/Condensate system & Clearance for vacuum pulling.
Mill Fire
a) Fire in mill under shut down:
Isolate the mill totally from air side by closing cold/hot air dampers & gates and mill seal air valves.
Shutdown Instructions
1 Ensure UT change over before tripping of boiler/ turbine.
2 Ensure 400 KV breaker are opened after unit tripping.
UPS Failure
CONSEQUENCES OF 240 VOLT UPS SUPPLY FAILURE:-
All LVS supplies from main UPS will not be available but from mini UPS supply will be
available for around 2 hours .
Boiler forced Cooling
1 In case of Tube leakage
1.1 After Tripping the boiler ,stop FD fan and keep ID fan running at
minimum load and ensure furnace pressure negative inside boiler.
CC(BCW) Pump Isolation & Purging
1. ISOLATION OF CC PUMP REMARKS
1.1 Remove from Stand by mode if it is in auto
1.2 Stop CC pump if running
Bunker fire : Prevention
PREVENTION OF BUNKER FIRE
Ensure Feeder outlet gate closes on auto when Feeder stopped/tripped. Otherwise give
a close command for closing.
Monday, May 18, 2020
Thursday, January 2, 2020
Wednesday, January 1, 2020
Condenser : One Pass Isolation
2 Decrease the load to 300 – 350 MW
3 Ensure that both CW interconnection valve are opened
4 Start Stand by Vacuum pump
Generator Air tightness Test
1) Air Filling valve is to be opened for flushing of line & removal of moisture in atmosphere.
2) Chemistry is to take sample for dew point measurement. After chemistry clearance , Filling process
has to be continued.
3) Close the waste gas (vent) valves.
APH Hot Washing
2 Both FD/ID/PA fans should be in stopped condition
3 All APH flue gas outlet damper should be closed
Stopping one FD Fan
2 Before Unloading FD Fan (to be stopped ),The following
Permissive & Protection to be kept bypassed :
“FD Fan ON & Discharge Gate close” permissive to be given
“FD Fan ON & Discharge gate auto open” to be bypassed.
Stopping one PA Fan
2 Keep 4 consecutive Mills in service. If required , take oil guns in service
Stopping one ID Fan
- Reduce Load to 300MW
- Start Unloading corresponding FD fan & increase loading of other FD Fan through blade pitch.
Stopping one PAPH
- Reduce Load to 300MW
- Slowly close flue gas outlet damper for PAPH which has to be stopped
Stopping one SAPH
- Reduce Load to 300MW
- Slowly close flue gas outlet damper (2 in no. )for APH which has to be stopped
- Adjust other PAPH/SAPH flue gas outlet damper
- Close flue gas inlet damper
- Close SCAPH inlet , outlet & bypass damper. During Closing , Observe Air Flow.
- Close SAPH air outlet damper (2 in no.)
- Stop the SAPH motor once flue gas inlet temperature reduced below 150deg C
- Close Air motor main isolating valve & bypass isolating valve
LIGHT UP CHECK POINTS
- MAN ,MATERIAL REMOVED AND BOILER IS READY FOR LIGHT UP.
Water-chemistry: 500 MW
1. Boiler Water – pH = 9.1-9.4
2. Boiler Water – Specific Conductivity < 20.0 μs/cm
3. Boiler Water – Silica < 100 ppb
4. Boiler Water - Phosphate = 1-2 ppm
5. Boiler Water - Chloride < 0.5 ppm