Saturday, May 12, 2018
Thursday, May 10, 2018
Stopping- Starting of 2nd PAPH
Stopping- Starting of 2nd PAPH | |||||||||||||||||
Each unit is provided with two bi-sector type regenerative primary air preheaters to recover the | |||||||||||||||||
heat from waste flue gas leaving from the furnace and utilised to preheat the primary air which inturn | |||||||||||||||||
used to dry the raw coal and transport pulverised coal powder from mill to the furnace through coal pipes. | |||||||||||||||||
Air pre-heater consists mainly rotor housing, cylindrical cellular rotor, guide and Support bearings, oil | |||||||||||||||||
systems for guide and support bearings, soot blower system, Stationary water washing devices & fire | |||||||||||||||||
fighting devices , auxiliary air motor drive with over-running clutch, oil carryover probe , inspection lights s | |||||||||||||||||
etc. The complete rotor is supported by a thrust bearing at the bottom and guided by the radial bearing at | |||||||||||||||||
the upper end. An air motor is provided to ensure the continued operation of the air pre-heater, even if | |||||||||||||||||
power to electric motor is interrupted. It may also be used to control speed of the rotor during water | |||||||||||||||||
washing of heating surfaces. | |||||||||||||||||
When ever one APH trips in a running Unit the run back operates & Unit load gets | |||||||||||||||||
reduced to 300 MW( 60 %) . Normally 4-5 Mill operation permissive is available with one APH out | |||||||||||||||||
of service . | |||||||||||||||||
PROCEDURE FOR STOPPING AND ISOLATION OF ANY SECOND PAPH: - | |||||||||||||||||
E-1 PRE CONDITION OF THE UNIT: - | |||||||||||||||||
1. Unit is running at full load (500MW) with 7 mills in operation. | |||||||||||||||||
2. Both TDBFPs are in service and Feed water control in auto. | |||||||||||||||||
3. MDBFP # C is available on auto (Rapid start up mode). | |||||||||||||||||
4. Unit control is in CMC mode. | |||||||||||||||||
5. Airflow control is in auto with both FD fans in service. | |||||||||||||||||
6. Both PA fans in operation in CAS mode with PA header pressure set at 820mmwc. | |||||||||||||||||
7. Both ID fans in service and furnace draft control in auto. | |||||||||||||||||
E-2 ENSURE THE FOLLOWING: | |||||||||||||||||
1. Running contact of other running PAPH. | |||||||||||||||||
2. Revise the station DC as per the planned shut down programme. | |||||||||||||||||
3. Availability of PAPH / SAPH soot blowers for operation. | |||||||||||||||||
4. Availability of auxiliary drive (air motor) of the PAPH (which is to be stopped). | |||||||||||||||||
5. All (4nos) economizer bypass dampers are closed. | |||||||||||||||||
6. Availability of atomizing steam and HFO at requisite pressure & temp (oil: 100ºC / 17-18 kg/cm², Steam: | |||||||||||||||||
200 – 210ºC / 6.5 kg/cm²). | |||||||||||||||||
7. Completion of WB/LRSB operation before starting the load reduction. | |||||||||||||||||
8. Best communication between control room and local. | |||||||||||||||||
9. Bypass TDBFP – A / B recirculation valve auto-closing protection. | |||||||||||||||||
10. Check for the healthiness of the mill outlet temperature low to feeder tripping protection for all running | |||||||||||||||||
mills, Normally it is set at 50 deg C. | |||||||||||||||||
PAPH STOPPING AND ISOLATION PROCEDURE: - | |||||||||||||||||
1. Take the unit control to manual from CMC mode. (Turbine on limit pressure control and Boiler master on | |||||||||||||||||
manual). | |||||||||||||||||
2. Take fuel master to manual and gradually reduce the load to 400MW by slowly unloading and removing | |||||||||||||||||
7th running mill. Check airflow according to the load (1650T/ hr corresponding to 400MW). | |||||||||||||||||
3. Take HFO support in one elevation corresponding to any running mill according to the mill combination | |||||||||||||||||
(At least 3 oil guns in one elevation). | |||||||||||||||||
4. Gradually reduce the load to 300MW by slowly unloading and removing 6th running mill. Check airflow | |||||||||||||||||
according to the load (1450T/ hr corresponding to 300MW). | |||||||||||||||||
5. Reduce MS pressure set point according to the load during the process of load reduction. | |||||||||||||||||
6. Check the loading and suction flow of TDBFP A / B. If suction flow is low corresponding to the speed, | |||||||||||||||||
Then keep open any one TDBFP- A / B recirculation valve. | |||||||||||||||||
7. Probably keep five consecutive mills in service to ensure stable combustion. | |||||||||||||||||
8. Observe and slowly reduce the PA header pressure set to 800mmwc from 850mmwc. | |||||||||||||||||
9. Adjust the burner tilt position to maintain MS & HRH temperature up to maximum possible (540C). | |||||||||||||||||
10. Gradually close the PAPH (which is to be stopped) air outlet damper from local & lock it mechanically | |||||||||||||||||
and simultaneously maintain the flue gas outlet temperature by closing the FG outlet damper of | |||||||||||||||||
corresponding PAPH. Adjust the other running PAPH & SAPH A/B FG outlet temperature from remote. | |||||||||||||||||
Then isolate the air outlet damper actuator power supply. This activity needs best communication | |||||||||||||||||
between control room and local. | |||||||||||||||||
11. Check the PA header pressure for any variation while closing air outlet damper and adjust it, if required. | |||||||||||||||||
12. Slowly close the air inlet damper from local and lock it mechanically. Isolate the power supply. | |||||||||||||||||
13. Observe the mill outlet temperature and accordingly adjust mill loading. | |||||||||||||||||
14. Close flue gas inlet damper from local and lock it mechanically. Isolate the power supply. | |||||||||||||||||
15. Close flue gas outlet damper from remote fully and lock it mechanically. It can be opened to 10% with the | |||||||||||||||||
help of C& I to create negative draft in side the APH if it is required by BMD. | |||||||||||||||||
16. Observe the mill outlet temperature and APH flue gas outlet temperatures accordingly adjust the running | |||||||||||||||||
PAPH & SAPH – A / B flue gas outlet dampers. | |||||||||||||||||
17. Start running PAPH and SAPH – A / B soot blowing. (This is to be done at least twice in a shift as long as | |||||||||||||||||
oil guns in service). | |||||||||||||||||
18. After stopping the PAPH, Gradually increase the load to approximately 330MW with 5 mills operation by | |||||||||||||||||
observing PA outlet temperature, mill outlet temperature and PA header pressure. | |||||||||||||||||
19. Remove oil support after stabilisation of load at approximately 330MW with 5 mills operation with safe | |||||||||||||||||
mill outlet temperature (Should be >60ºC). | |||||||||||||||||
20. Keep PRAPH in service for attending any work outside the APH like air outlet duct fabric compensator | |||||||||||||||||
repair work. | |||||||||||||||||
21. Stop the PAPH (which is to be stopped) after cooling (air outlet side manhole can be kept open for | |||||||||||||||||
cooling) to normal temperature so that maintenance can be done and isolate the power supply of PRAPH | |||||||||||||||||
drive motor. | |||||||||||||||||
22. Close both main and bypass airlines for air motor. | |||||||||||||||||
23. Press the local EPB of the PAPH (which is stopped). | |||||||||||||||||
24. Issue PFW after ensuring proper isolation according to PFW procedure. | |||||||||||||||||
E-4 PROCEDURE FOR NORMALISATION AND STARTING PRAPH: - | |||||||||||||||||
1. Revise the station DC as per the planned programme. | |||||||||||||||||
2. Ensure the cancellation of PTW and clearance from maintenance BMD/EMD/C&I, then normalise the | |||||||||||||||||
drive motor power supply. | |||||||||||||||||
3. Check the PAPH for proper boxup (check all manholes are closed). | |||||||||||||||||
4. Check the PAPH by running air motor for any abnormal rubbing. | |||||||||||||||||
5. Normalise the drive motor power supply. | |||||||||||||||||
6. Release the local EPB. | |||||||||||||||||
7. Stop PAPH air motor and start main electric motor. | |||||||||||||||||
8. Normalise the air outlet damper power supply. Remove the lock and slowly open the PAPH air outlet | |||||||||||||||||
damper from local. | |||||||||||||||||
9. Normalise the flue gas inlet damper power supply. Remove the lock and slowly open the PAPH flue gas | |||||||||||||||||
inlet damper from local. | |||||||||||||||||
10. Slowly Increase the PA header pressure set point to normal (820mmwc) and wait for stabilisation of the | |||||||||||||||||
header pressure. | |||||||||||||||||
11. Normalise the air inlet damper power supply. Remove the lock and slowly open the air inlet damper from | |||||||||||||||||
local. Simultaneously open flue gas outlet damper from remote and maintain the flue gas outlet | |||||||||||||||||
temperature and observe PA header pressure while opening air inlet damper. | |||||||||||||||||
12. Take 6th mill into service and gradually increase the load to 450MW. | |||||||||||||||||
13. Adjust the MS pressure set point according to the variation of load. | |||||||||||||||||
14. Close TDBFP-A / B recirculation valve (which was kept opened previously) after sufficient loading of both | |||||||||||||||||
TDBFPs. | |||||||||||||||||
15. Take 7th mill into service and increase the load to full (500MW). | |||||||||||||||||
16. Adjust the FG outlet damper positions of PAPH – A / B and SAPH – A / B after stabilization of load. | |||||||||||||||||
17. Adjust the burner tilt to maintain M S & HRH temperature up to maximum possible (540C). | |||||||||||||||||
18. Normalise the TDBFPs recirculation control valve auto close protection. | |||||||||||||||||
19. Put fuel master in auto. | |||||||||||||||||
20. Transfer the unit control from manual to CMC mode. |
BCW Pump
BCW Pump | ||||||||||
STARTING THE BCW PUMP : - | ||||||||||
F.1 PRE START CHECKS BEFORE INITIAL STARTING OF THE PUMP | ||||||||||
1 Boiler Drum is filled & drum level is maintained on positive side (+200 mm) for starting first | ||||||||||
pump. | ||||||||||
2 SGECW System & BCW Booster Pump is in service. | ||||||||||
3 Emergency over head tank level OK. | ||||||||||
4 Ensure that pump & pump cooler is completely vented. | ||||||||||
5 Start permissive is available. | ||||||||||
6 LP cooling water valves are open and the cooling water flow is > 75 LPM. | ||||||||||
7 All other valves must be closed. | ||||||||||
8 LP & HP purge lines are charged and purge line valve to motor is in closed condition. | ||||||||||
9 Check for any water leakage from pump instruments, cooler vent, pump & motor assembly. | ||||||||||
10 With water filled, the insulation resistance measured at the terminal links, using a 1000V | ||||||||||
megger must exceed 200 mega ohms. | ||||||||||
START PERMISSIVE | ||||||||||
1 No Switchgear disturbance. | ||||||||||
2 Switchgear Available | ||||||||||
3 Drum N2 Vent Valves Closed. | ||||||||||
4 Motor Cavity Temp Not high (57° C). | ||||||||||
5 Suction Manifold / Casing DT not high (< 38° C). | ||||||||||
6 BCW P/P Cooling Water Flow Adequate (> 75 LPM). | ||||||||||
7 BCW P/P Not Tripped. | ||||||||||
8 Both Discharge v/v Stem open. | ||||||||||
9 When a boiler is started from cold, a minimum of two BCW pumps must be operated. It is | ||||||||||
normal practice to start all the three pumps before boiler light up | ||||||||||
Starting of pumps | ||||||||||
1 Start the first pump | ||||||||||
2 Motor current will drop from full starting current after few seconds to normal & there is no | ||||||||||
hunting in current. | ||||||||||
3 Ensuring Drum level is normal start second pump (after starting of pump it tends to dip). | ||||||||||
4 Differential pressure should rise immediately to approx. 3.1 kg/sec². | ||||||||||
5 Check with local operator about any abnormal sound from pump. | ||||||||||
6 Ensure for the standby pump that DT between pump casing & boiler water is within 56° C. | ||||||||||
7 Caution –If motor fails to start after 5 seconds, press stop button & do not attempt to | ||||||||||
start the pump for 20 minutes. | ||||||||||
FOR STANDBY BCW PUMP: | ||||||||||
1 Close the service valve in pump jumper line & open the pump discharge by-pass valve. This | ||||||||||
ensures that as the boiler heats up, a flow passes from the discharge legs to the pump case & | ||||||||||
impeller. | ||||||||||
2 Check the motor cavity temperature is not exceeding 49 ° C. | ||||||||||
3 In such a case take the pump in service & close pump discharge by-pass valve & open the | ||||||||||
pump jumper line service valve. | ||||||||||
ISOLATION PROCEDURE | ||||||||||
There is no provision to isolate the pump in boiler lighted up condition as no isolation | ||||||||||
v/v is provided in suction line, only two manual v/v are provided in the two discharge | ||||||||||
lines. | ||||||||||
PROTECTIONS | ||||||||||
1 PUMP Motor Cavity Temperature Very High with a time delay of 5 sec (> 60 ° C). | ||||||||||
2 Discharge Valve Stem-1 not open | ||||||||||
3 Discharge Valve Stem-2 not open |
BAHP -BALP
BAHP -BALP | |||||||||||||||
Low pressure ash water system caters water at the following areas (BALP pumps): | |||||||||||||||
1. Ash slurry sump makeup. | |||||||||||||||
2. Ring header for seal trough makeup / flushing. | |||||||||||||||
3. Refractory cooling supply. | |||||||||||||||
4. Bottom ash hopper makeup / filling. | |||||||||||||||
5. Bottom ash hopper window spray. | |||||||||||||||
6. Make up to overflow settling bin. | |||||||||||||||
High pressure water pump caters water at the following areas (BAHP pumps): | |||||||||||||||
1. Jet pump fitted below the clinker crusher at the bottom ash hopper. | |||||||||||||||
2. Jetting water requirement for bottom ash hopper. | |||||||||||||||
3. HP line water supply to feeder ejector and slurry box of economizer and economizer | |||||||||||||||
bypass system. | |||||||||||||||
4. HP line to economizer ash transfer hopper for jetting purposes. | |||||||||||||||
5. HP line to jet pump fitted below the economizer ash transfer hopper. | |||||||||||||||
6. HP line bypass connection to bottom ash hopper refractory cooling water and ring | |||||||||||||||
header for seal trough make up / flushing water line. | |||||||||||||||
7. Flushing connections to bottom ash hopper overflow weir boxes. | |||||||||||||||
8. Line for flushing sludge pump discharge lines. | |||||||||||||||
Flushing water pump: | |||||||||||||||
1. The flushing water pumps are provided for slurry disposal line flushing purpose. | |||||||||||||||
Sump jetting water pumps caters at the following areas: | |||||||||||||||
1. Ash slurry sump jetting. | |||||||||||||||
2. Common ash slurry trough jetting arrangement. |
Control Fluid system
Control Fluid system | |||||||
Control fluid (A fire resistant fluid) is used as operating media for oil operated HP & IP stop / | |||||||
control valves. This control fluid system also supplies control fluid as operating media for LPBP | |||||||
stop & control valves. The control fluid system contains two 100 % capacity pumps with double | |||||||
discharge i.e. LP control fluid delivered at 8 bar pressure from the 1st stage of the pump and HP | |||||||
control fluid delivered at 32 bar pressure from the pump 4th stage, two coolers (one being standby). | |||||||
There is no common filter, each sub system has got its own Duplex or rotating filters. CF | |||||||
tank is provided with two oil vapour exhausters, which extracts non condensable gases from the | |||||||
tank and expels to atmosphere. There is a temperature control valve which Controls oil | |||||||
temperature by controlling oil flow through the cooler. There is an electrical heater provided in the | |||||||
control fluid tank to maintain the oil temperature between 55 and 57ºC. | |||||||
Heater gets ON - If CF temperature in tank < 55ºC or at heater <50ºC. | |||||||
Heater gets OFF- If CF temperature in tank >57ºC or at heater >65ºC. | |||||||
Control fluid regeneration system is provided for removal of acids and ageing products | |||||||
during operation by the continuous filtering through Fuller´s earth and mechanical filters. The | |||||||
mode of operation of this natural earth treatment is based on a ion-exchange reaction. The | |||||||
regeneration system is having two pumps, two filters, two Fuller Earth filters, one heater. | |||||||
FULLER EARTH REPLACEMENT PROCEDURE: | |||||||
F.1 Isolation procedure of fuller earth for replacement :- | |||||||
1 Stop the regeneration pumps and isolate the power supply. | |||||||
2 Close inlet and outlet valves of the fuller earth system. | |||||||
3 Open vent valves of the fuller earth system for depressurization. | |||||||
4 Open drain valve of the fuller earth system for draining. | |||||||
5 Ensure the complete draining of the system. | |||||||
6 Issue PTW on fuller earth system for fuller earth replacement. | |||||||
F.2 Normalization procedure of fuller earth after replacement:- | |||||||
1 Close the drain valves of fuller earth system. | |||||||
2 Crack open the vent valve of fuller earth system. | |||||||
3 Slowly open inlet valve and ensure venting. | |||||||
4 Close the vent valve of fuller earth system after venting. | |||||||
5 Allow it for soaking about 4-5 hours if new fuller-earth is used. | |||||||
6 Open outlet valve of fuller earth system. | |||||||
7 Normalise the regeneration pump power supply. | |||||||
8 Start regeneration pump and check for any abnormality. | |||||||
G PROCEDURE FOR FILTER CHANGE-OVER:- | |||||||
1 Close drain valve of stand-by filter. | |||||||
2 Open vent valve of stand-by filter. | |||||||
3 Open equalizing valve and observe the pressure in the pressure gauge mounted on stand-by | |||||||
filter. Also observe the temperature of the stand-by filter body which will increase. | |||||||
4 Close the vent valve and equalizing valve after ensuring pressure and temperature of the | |||||||
standby filter. | |||||||
5 Slowly change-over the filter by rotating the change-over valve. | |||||||
6 Open the vent for depressurization and check the pressure. | |||||||
7 Open the drain valve of the new stand-by filter and ensure the complete draining (Continuous | |||||||
draining may happen when filter was not properly isolated due to passing in change over valve) | |||||||
PUMP INITIAL STARTING AND STOPPING PROCEDURE: | |||||||
1 All PTWs are returned and Clearance from Turbine Maintenance available | |||||||
2 Pump surroundings are clean & properly illuminated and access to the pump area is adequate. | |||||||
3 No PTW pending in the Governing system (Main and LP Bypass) & lined up. | |||||||
4 Control fluid moisture and acidity values are within limits (Moisture: <1000 ppm (mg/kg) / Acidity : | |||||||
<0.1 mg KOH/Gm). | |||||||
5 CFT level is more than + 100 mm and that CF temp. is more than 20ºC | |||||||
6 Start one control fluid pump and stop it after a few seconds to allow for line filling and venting. | |||||||
7 Then again start the pump and keep in service. | |||||||
8 Check that the HP & LP pressure are more than 32 ksc and 8 ksc respectively. | |||||||
9 Check for any abnormality like Abnormal sound, seal leakage, bearing temp. line leakage, | |||||||
Vibration etc. Stop the pump if any major abnormality is observed. | |||||||
10 Observe the CFT level after starting the pump. If it drops below zero and maintains there, level | |||||||
topping up may be required. | |||||||
11 Similarly check the availability of other pump (Stop the running pump and then start the stand by | |||||||
pump). Check that the HP & LP pressure are more than 32 ksc and 8 ksc respectively. | |||||||
12 Check for any abnormality like Abnormal sound, seal leakage, bearing temp. line leakage, | |||||||
Vibration etc. Stop the pump if any major abnormality is observed. | |||||||
13 Keep any one pump in service. | |||||||
14 Observe for any filter choking. If required changeover and clean the filters. | |||||||
15 Switch on the control fluid heating system and put it in auto. | |||||||
16 Observe the proper operation of the CF temp. control valve for maintaining the temperature. | |||||||
17 Switch ‘ON’ SLC CF system and give ‘Run’ command to complete the start-up | |||||||
TANK DRAINING AND REFILLING PROCEDURE | |||||||
I.1 CONTROL FLUID TANK DRAINING PROCEDURE | |||||||
1 Ensure that the unit is under shutdown and there is no requirement of control fluid system | |||||||
operation. | |||||||
2 Stop the both control fluid pumps and isolate the power supply. | |||||||
3 Stop both CF oil vapour exhausters and isolate the power supply. | |||||||
4 Stop both CF regeneration pumps and isolate the power supply. | |||||||
5 Ensure the availability of empty clean oil barrels or empty standby thoroughly cleaned tank | |||||||
prepared for this purpose for emptying the CF tank. | |||||||
6 Ensure the clearance from TMD for emptying the CF tank.. | |||||||
7 Isolate the deluge valve spray system provided for the system | |||||||
8 Note down the tank level before starting draining. | |||||||
9 TMD is responsible for tank draining into the empty barrels. | |||||||
I.2 CONTROL FLUID TANK FILLING PROCEDURE | |||||||
1 Ensure the correct quality of the control fluid ((Moisture: <1000 ppm (mg/kg) / Acidity : <0.1 mg | |||||||
KOH/Gm). | |||||||
2 Ensure the inspection of the tank is completed and cleanliness of the tank. | |||||||
3 Ensure the CFT drain valve is closed. | |||||||
4 Local level gauge is calibrated if required and charged condition. | |||||||
5 TMD is responsible for tank filling from the barrels. | |||||||
6 Start CFT filling and monitor the level. | |||||||
7 Check the Level switches (Operation & resetting) while filling CFT. | |||||||
8 Fill the CFT level up to 650mm from Top | |||||||
9 Check oil level in the local level gauge and compare with remote level indication, Attend it if any | |||||||
deviation appears.. | |||||||
10 CFT filling completed | |||||||
J CONTROL FLUID PUMP CHANGE OVER | |||||||
1 Check & note down the running pump discharge pressure. | |||||||
2 Check & note down the running pump current at UCB & local breaker panel. | |||||||
3 SLC control fluid in ON condition. | |||||||
4 Start standby control fluid pump from UCB CRT. | |||||||
5 Check the discharge header pressure at local and UCB. Ensure that there is an increase in | |||||||
pressure, which indicates loading condition of the standby pump. | |||||||
6 Check the current of the running standby pump at UCB and local breaker panel. | |||||||
7 Stop the previous running pump after ensuring loading condition of the standby pump. | |||||||
8 Again check the discharge header pressure and current (There may be a dip in discharge | |||||||
pressure). | |||||||
CHECKS AND MONITORING DURING NORMAL RUNNING:- | |||||||
K.1 Local Monitoring: | |||||||
1 Note down CF tank level. CFP discharge pressure, all filters DP, cooler o/l temp, tank temp, | |||||||
Waste fluid tank level. | |||||||
2 Check for any leakages and abnormal sound, foaming condition. | |||||||
K.2 Remote Monitoring: | |||||||
1 CF tank level, cross-check it with local reading. | |||||||
2 CFP discharge pressure, temp after cooler, pump current, see trend of current and pressure to | |||||||
detect foaming condition. | |||||||
3 See the moisture content and acidity from daily planning report and take necessary action if any | |||||||
discrepancy occurs. |
Subscribe to:
Posts (Atom)