| BAHP -BALP | |||||||||||||||
| Low pressure ash water system caters water at the following areas (BALP pumps): | |||||||||||||||
| 1. Ash slurry sump makeup. | |||||||||||||||
| 2. Ring header for seal trough makeup / flushing. | |||||||||||||||
| 3. Refractory cooling supply. | |||||||||||||||
| 4. Bottom ash hopper makeup / filling. | |||||||||||||||
| 5. Bottom ash hopper window spray. | |||||||||||||||
| 6. Make up to overflow settling bin. | |||||||||||||||
| High pressure water pump caters water at the following areas (BAHP pumps): | |||||||||||||||
| 1. Jet pump fitted below the clinker crusher at the bottom ash hopper. | |||||||||||||||
| 2. Jetting water requirement for bottom ash hopper. | |||||||||||||||
| 3. HP line water supply to feeder ejector and slurry box of economizer and economizer | |||||||||||||||
| bypass system. | |||||||||||||||
| 4. HP line to economizer ash transfer hopper for jetting purposes. | |||||||||||||||
| 5. HP line to jet pump fitted below the economizer ash transfer hopper. | |||||||||||||||
| 6. HP line bypass connection to bottom ash hopper refractory cooling water and ring | |||||||||||||||
| header for seal trough make up / flushing water line. | |||||||||||||||
| 7. Flushing connections to bottom ash hopper overflow weir boxes. | |||||||||||||||
| 8. Line for flushing sludge pump discharge lines. | |||||||||||||||
| Flushing water pump: | |||||||||||||||
| 1. The flushing water pumps are provided for slurry disposal line flushing purpose. | |||||||||||||||
| Sump jetting water pumps caters at the following areas: | |||||||||||||||
| 1. Ash slurry sump jetting. | |||||||||||||||
| 2. Common ash slurry trough jetting arrangement. | |||||||||||||||
Thermal Power Plant Operation Information guide. Please find here the Stand ard Operating Procedures, Instructions to operate various capacity Thermal power plants in India. This is as per my experience and any abnormality found please refer other sources. Thank you.
Thursday, May 10, 2018
BAHP -BALP
Subscribe to:
Post Comments (Atom)
-
HP & LP Bypass Operation and Protection Purpose Boiler operation independent of the turbine Minimum steam flow through SH &...
-
Generator Air Tightness Test Period Of Test= 24 Hrs without a Break Air Pressure Drop (Allowed in 24 Hrs) : <=0.15 ksc Air Test Pre...