ATRS Rolling: 500 MW
CHECKLIST FOR ROLLING THROUGH ATRS (HOT start up)
PRESENT CONDITION:
CHECK LIST
PROCEDURE OF STARTING ATRS
RAISING SPEED UPTO 3000 RPM
BEFORE SYNCHRONISATION
SYNCHRONISATION IN AUTO FROM ELECTRICAL VERTICAL PANNEL
Immediately after Synchronization
PRESENT CONDITION:
- M/C on barring
- MS temp : >480 Deg /Pressure : 90 ksc
- HRH temp : >460 Deg /pressure : 9 ksc
- Lube oil temperature : 55 deg
- CF temperature : > 50 deg
- PW/CG/CF temperature control valves in auto
- Speed controller active
CHECK LIST
- Turbine in Reset condition ( Trip oil pressure : > 8 ksc)
- Starting device: 0% / Speeder gear : 99%
- HP & IP CVs showing : 0%
- Turbine throttle pressure set point 0 ksc
- MAL 11 & MAL 12 in open condition/ all MAL drains manual valve open /SLC drains ON
- Load contol On / Limit pressure mode selected
- MS 109 / MS 110 & HRH 105/106 valves open feedback
- Load refrence (PR) set point to be 70 MW/ PRmax 120 MW
- Trim device to be made off
- Check TSC margins &TSC influence on
- Plunger coil not off
- check X1 &X2 criteria for opening of STOP valves
- Temperature curves X3,X4& X5 for control valve opening and upto 360 rpm
- Reset all relays in the GRP panel
- Lube oil temperature set point to be kept at 45 deg.
PROCEDURE OF STARTING ATRS
- Check all start permissives are coming
- Ensure normal mode is displayed in ATRS mimic
- Select A/M from SGC turbine tile
- To start the programme press startup from the tile
- Check for closing of MAL 11 & MAL 12 in STEP 3
- Observe starting device raise command in STEP no 5 and stop valve opening( SD > 42%)
- Observe in STEP -8 that MAL 11 & 12 control goes to auto
- Step no.9 TRACKING DEVICE gets ON followed by opening of IP stop valves ( SD >56%)
- Check that in STEP -11 MAL 11& 12 opens in manual mode
- Check in step no-12 turbine speed set point increasing upto 360 RPM and accordingly the actual speed .
- Hold the programme in step no 12 if required (criteria not satisfied) by pressing A/M from SGC turbine tile.
- Ensure closing of barring valve at 240 rpm otherwise close it manually.Mot level will increase
- Soaking time for Hot start up 180 sec
- Check for closing of MAL 11 & 12 .
RAISING SPEED UPTO 3000 RPM
- Check TSC margin >30
- Check X6 criteria is satisfied (Ensure opening of MAL 11& 12 in manual )
- Check speed margin (600 mw/min)
- Sufficient margin in HP bypass
- Switch on the ATRS programme (Auto) & start
- Speed set point will increase upto 3000 rpm in STEP -16 and actual speed will raise accordingly
- Switch OFF the programme once speed set point reaches 3000 rpm
- Observe JOP stopping at 540 rpm & AOP at 2850 rpm
- Check vibration /Brg temperatures & other TSI parameters
- Change the lube oil filter if required
- LPBP in Auto with pr setpoint around 8 KSC.
- Check for HP (below 95 deg ) / IP casing DT before synch(below 40 deg)
BEFORE SYNCHRONISATION
- Check X7 criteria
- Close the field breaker & made excitation On (one AVR will come in auto)
- After excitation ON observe voltage build up 90% of 21kv (19kv)
- Slowly voltage raise up to 21kv & Adjust the generator terminal voltage
SYNCHRONISATION IN AUTO FROM ELECTRICAL VERTICAL PANNEL
- Select the GCB
- Switch ON the synchroscope
- Select the mode to ATRS by selection key
- Switch on the AUTO synchronizer from the vertical panel
- GCB closes in auto at 12 o clock
- Observe speed setpoint raises by 15 rpm as per logic other wise give one raise pulse to speed set point so that unit comes to block load .
- Unit is synchronised
Immediately after Synchronization
- Increase the Speed reference and maintain the unit load around 50 MW
- After ensuring all parameters are normal increase the load set point to 70 -75 MW by increasing the load reference.
- Change over the Turbine control from Speed to Load by increasing the load reference.
- While changing the control from speed to load always ensure that LP bypass is in auto, No hunting in IP Control valves, and increase the load set point in such a way that the IPCV opening to 100%.
- After IPCVs full open increase the load set point further and slowly close the HP bypass.
- After closing the HP bypass close the LP .
- After unit load more than 150 MW only keep machine in pressure control, if required.
- Charge the LP & HP heaters.