Thursday, September 4, 2025

Dadri S/Y Line loading

 

                                                      NTPC-DADRI TRANSMISSION LINE LOADING

 

Lines                         conductor           SIL             CA           Cent clair     stability       thermal             operation

                                                                                                    graph mw       mw          limit mw             limit mw

 

Maharanibag  54km                            692          2371              2371        5896               1962                 1962

Mandaula 1&2  46km                         692           2533             2533        6923                1962                 1962

Greater Noida 13 km                          692           3679             3679       24179              1962                 1962

Malerkotla 297 km                             517             560                692           811                852                    852

Panipat 1&2  112 km                          517             1247            1247          2145             852                 852

Murad nagar  33 km                           517              2143            2143          7280             852                 852

 

  SIL- SURGE IMPEDENCE LOADING

    CA- CENTRAL ELECTRICITY AUTHORITY

 

NTPC-DADRI (4*210 +2*490 THERMAL + 830 MW GAS + 5 MW SOLAR )( SWITCHYARD 220/400KV ,5*500 MVA)

                                             OUT GOING  400 KV TRANSMISSION LINES

 

DADRI------13KM-------àG,NOIDA(UP)(3*315+1*500MVA)----------22KM-àNAVADA(UP)-------21kmà BALLABGARH(PG)

DADRI-------54km------à MAHARANIBAGH(PG)(2*315+2*500MVA)---- 61KM---à BALLABGARH (PG)(11 LINES)(5*315MVA)

DADRI------33KM-------à MURAD NAGAR(UP)(3*315MVA)( 4LINES TO RISHIKESH/KANPUR/ALIGARH/DADRI)

DADRI------117KM---TWO LINES---àPANIPAT 1&2(BBMB) (2*450MVA)(3 LINES- 2 FROM DADRI+1 FROM MEERUT)

DADRI------297KM-----àMALERKOTLA(PG)(2*315+1*500MVA)(3 LINES FROM PATIYALA/LUDHIANA/DADRI)

DADRI----- 44KM---TWO LINES----àMANDAULA 1&2 (PG) (4*315MVA)(8LINES,4TO MEERUT+2BAWANA+2DADRI)

DADRI------54KM---TWO LINES----à LONI OR HARSH VIHAR 1 &2(UP) ( 2*315 MVA) ( 2 LINES FROM DADRI ONLY )

DADRI—400KV BUS 1&2 TO HVDC(PG)----à 2*750 MW HVDC BIPOLE LINE 815 KM TO RIHAND THERMAL