| MOT Centrifuge | ||||||||||||
| 1. Drain the anti flood tank and close the drain valve after draining. | ||||||||||||
| 2. Ensure water level in heater is adequate | ||||||||||||
| 3. Check that level in gear box is normal. | ||||||||||||
| 4. Ensure make-up water for the heater tank and seal water is available. | ||||||||||||
| 5. Ensure MOT oil level is > minimum | ||||||||||||
| 6. Line up oil from MOT (clean oil section or dirty oil section) to centrifuge suction. | ||||||||||||
| 7. Ensure the manual valve in air locking unit (adjacent to MOT) is open. | ||||||||||||
| 8. Open the manual valve in return line from centrifuge to MOT | ||||||||||||
| Operation | ||||||||||||
| 1. start the Centrifuge | ||||||||||||
| 2. Put all Heater in auto | ||||||||||||
| 3. Open seal water line when Centrifuge speed is stable: for 2.5 minutes to make seal | ||||||||||||
| 4. after sealing is achieved, close sealing valce | ||||||||||||
| 5. Open suction valve of centrifuge | ||||||||||||
| 6. Check centrifuge oil outlet pr>1 ksc to 1.5 ksc, if not throttle outlet valve to maniatain it | ||||||||||||
Thermal Power Plant Operation Information guide. Please find here the Stand ard Operating Procedures, Instructions to operate various capacity Thermal power plants in India. This is as per my experience and any abnormality found please refer other sources. Thank you.
Thursday, May 10, 2018
MOT Centrifuge : Operation
Subscribe to:
Post Comments (Atom)
-
HP & LP Bypass Operation and Protection Purpose Boiler operation independent of the turbine Minimum steam flow through SH &...
-
Generator Air Tightness Test Period Of Test= 24 Hrs without a Break Air Pressure Drop (Allowed in 24 Hrs) : <=0.15 ksc Air Test Pre...