CW PASS ISOLATION PROCEDURE: |
PRE CONDITION OF THE UNIT: - |
|
1 Unit is running at full load (500MW) with 7 mills in
operation. |
2 Both TDBFPs are in service and Feed water control in
auto. |
3 MDBFP # C is available on auto (Rapid start up mode). |
4 Unit control is in CMC mode / manual mode. |
5 Both PA fans and FD fans are in service. |
|
6Both condenser circulating water passes in service. |
7 One condenser vacuum pump in service and other is
available in standby. |
8 Vacuum is maintaining normal i.e. - 0.90 kg/cm². |
9 Both ID fans in service and furnace draft control in
auto. |
10 All four CW pumps (Two pumps per unit) are in service
with both units interconnection valves are in open |
condition. Discharge header pressure normal (approx: 1.4
kg/cm²). |
|
|
|
|
|
ENSURE THE FOLLOWING : |
|
|
Revise the station DC as per the planned shut down
programme. |
2 Availability of atomizing steam and HFO at requisite
pressure & temp (oil: 100ºC / 17-18 kg/cm², Steam: 200 – |
210ºC / 6.5 kg/cm²). |
|
|
|
3 Completion of WB/LRSB operation before starting the
load reduction. |
4 Availability of PAPH / SAPH soot blowers for operation. |
5 Availability of second (standby) condenser vacuum pump. |
6 Stop corresponding CW pass OLTC after collection of
balls before starting CW pass isolation process. |
7 Take care of ACW pump suction header pressure very low
and discharge header pressure very high protection of |
the pumps in both corresponding units (ACW suction and
discharge header pressure may vary by 0.2kg/cm²). |
8 All CT fans (20 fans per each unit) are in service. |
9 Check and record CW pump discharge header pressure (CW
discharge header pressure may raise approximately |
0.2 Kg/cm² after isolation of one pass). |
|
10 Best communication system between local and control
room. |
11 Availability of condenser pit sump pumps and sump
level is normal. |
12 Take care of TDBFP – A / B recirculation valve
auto-closing when starting the load reduction. |
|
|
|
|
|
PROCEDURE FOR CW PASSES ISOLATION: - |
1 Start standby vacuum pump and check vacuum. |
2 Take the unit control to manual from CMC mode. (Turbine
on limit pressure control and Boiler master on manual). |
3 Take fuel master to manual and gradually reduce the
load to 400MW by slowly unloading and removing 7th running |
mill. |
|
|
|
|
4 Take HFO support in one elevation corresponding to any
running mill according to the mill combination (At least 3 |
oil guns in one elevation). |
|
|
5 Gradually reduce the load to 300MW by slowly unloading
and removing 6th running mill. Check airflow according to |
the load (1450T/ hr corresponding to 300MW). |
6 Reduce MS pressure set point according to the load
during the process of load reduction. |
7 Check the loading and suction flow of TDBFP A / B. If
suction flow is low corresponding to the speed, Then keep |
open any one TDBFP- A / B recirculation valve. |
8 Preferably kept five consecutive mills in service to
ensure stable combustion. |
9 Start PAPH – A / B and SAPH – A / B soot blowing. (This
is to be done at least twice in a shift as long as oil guns in |
service). |
|
|
|
|
10 Isolate the vacuum line manual isolation valve
provided corresponding to the CW pass which is to be isolated at |
the condenser end (8.5m near LPBP). |
|
11 Switch of the CW pass (which is to be isolated) inlet
valve power supply, Then gradually close the inlet valve |
manually from local and simultaneously observe the
vacuum, CW discharge header pressure. After full closing, |
Isolate the actuator power supply. |
|
12 Switch of the CW pass (which is to be isolated) outlet
valve power supply, Then gradually close the outlet valve |
manually from local and simultaneously observe the
vacuum, CW discharge header pressure. After full closing, |
Isolate the actuator power supply. |
|
13 Open the corresponding condenser water box vent valves
(2nos) for depressurisation. |
14 Open the drain valve provided in the corresponding
water box for draining after depressurisation. |
15 If draining of inlet water duct is started, then check
sump level and put sump pumps in auto or start / stop |
condenser pit sump pump for dewatering manually. |
16 Further tighten inlet and outlet valves if there is
any passing. |
17 After isolation of CW pass, Gradually increase the
load to approximately 350MW with 5 mills operation and |
simultaneously monitor condenser vacuum. |
18 Close TDBFP – A / B recirculation valve, which was
kept opened previously after sufficient loading of both |
TDBFPs. |
|
|
|
|
19 Remove oil support after stabilisation of load at
approximately 350MW with 5 mills operation. |
20 Issue PFW after ensuring complete draining and proper
isolation. |
|
|
|
|
|
PROCEDURE FOR CW PASSES NORMALISATION: - |
Revise the station DC as per the planned programme. |
2 Ensure the cancellation of PFW and clearance from
maintenance (TMD). |
3 Ensure the complete box up of the CW pass. |
4 Close the drain valve provided at the bottom of the
corresponding water box. |
5 Open the vent valves provided at the top of the
corresponding water box. |
6 Crack open the CW pass (which is isolated) inlet valve
manually from local and observe the CW discharge header |
pressure. |
|
|
|
|
7 Ensure air is coming from the vent line and close it
after ensuring complete venting. |
8 Gradually full open the CW pass (which is isolated)
inlet valve manually from local and observe the CW discharge |
header pressure. |
|
|
|
9 Gradually open the CW pass (which is isolated) outlet
valve from local manually and observe the vacuum and CW |
discharge header pressure. |
|
|
10 Normalise the inlet and outlet valve actuator power
supply |
11 After full opening of CW pass inlet and outlet valves,
Open the corresponding CW pass vacuum line manual |
isolation valve at 8.5m near LPBP, which is isolated
previously. |
12 Take 6th mill into service and gradually increase the
load to 450MW. |
13 Adjust the MS pressure set point according to the
variation of load. |
14 Take 7th mill into service and increase the load to
full (500MW). |
15 Adjust the burner tilt to maintain M S & HRH
temperature up to maximum possible (540C). |
16 Take care of TDBFP – A /B recirculation control valve
auto close protection. |
17 Take care of ACW pump suction header pressure very low
and discharge header pressure very high protection in |
both corresponding units. |
|
|
18 Put fuel master in auto. |
|
|
19 Take corresponding CW pass OLTC into service. |
20 Stop second vacuum pump and check vacuum. |
21 Take unit control in to CMC mode. |
|
Comments
Post a Comment