CW PASS ISOLATION PROCEDURE: | ||||
PRE CONDITION OF THE UNIT: - | ||||
1 Unit is running at full load (500MW) with 7 mills in operation. | ||||
2 Both TDBFPs are in service and Feed water control in auto. | ||||
3 MDBFP # C is available on auto (Rapid start up mode). | ||||
4 Unit control is in CMC mode / manual mode. | ||||
5 Both PA fans and FD fans are in service. | ||||
6Both condenser circulating water passes in service. | ||||
7 One condenser vacuum pump in service and other is available in standby. | ||||
8 Vacuum is maintaining normal i.e. - 0.90 kg/cm². | ||||
9 Both ID fans in service and furnace draft control in auto. | ||||
10 All four CW pumps (Two pumps per unit) are in service with both units interconnection valves are in open | ||||
condition. Discharge header pressure normal (approx: 1.4 kg/cm²). | ||||
ENSURE THE FOLLOWING : | ||||
Revise the station DC as per the planned shut down programme. | ||||
2 Availability of atomizing steam and HFO at requisite pressure & temp (oil: 100ºC / 17-18 kg/cm², Steam: 200 – | ||||
210ºC / 6.5 kg/cm²). | ||||
3 Completion of WB/LRSB operation before starting the load reduction. | ||||
4 Availability of PAPH / SAPH soot blowers for operation. | ||||
5 Availability of second (standby) condenser vacuum pump. | ||||
6 Stop corresponding CW pass OLTC after collection of balls before starting CW pass isolation process. | ||||
7 Take care of ACW pump suction header pressure very low and discharge header pressure very high protection of | ||||
the pumps in both corresponding units (ACW suction and discharge header pressure may vary by 0.2kg/cm²). | ||||
8 All CT fans (20 fans per each unit) are in service. | ||||
9 Check and record CW pump discharge header pressure (CW discharge header pressure may raise approximately | ||||
0.2 Kg/cm² after isolation of one pass). | ||||
10 Best communication system between local and control room. | ||||
11 Availability of condenser pit sump pumps and sump level is normal. | ||||
12 Take care of TDBFP – A / B recirculation valve auto-closing when starting the load reduction. | ||||
PROCEDURE FOR CW PASSES ISOLATION: - | ||||
1 Start standby vacuum pump and check vacuum. | ||||
2 Take the unit control to manual from CMC mode. (Turbine on limit pressure control and Boiler master on manual). | ||||
3 Take fuel master to manual and gradually reduce the load to 400MW by slowly unloading and removing 7th running | ||||
mill. | ||||
4 Take HFO support in one elevation corresponding to any running mill according to the mill combination (At least 3 | ||||
oil guns in one elevation). | ||||
5 Gradually reduce the load to 300MW by slowly unloading and removing 6th running mill. Check airflow according to | ||||
the load (1450T/ hr corresponding to 300MW). | ||||
6 Reduce MS pressure set point according to the load during the process of load reduction. | ||||
7 Check the loading and suction flow of TDBFP A / B. If suction flow is low corresponding to the speed, Then keep | ||||
open any one TDBFP- A / B recirculation valve. | ||||
8 Preferably kept five consecutive mills in service to ensure stable combustion. | ||||
9 Start PAPH – A / B and SAPH – A / B soot blowing. (This is to be done at least twice in a shift as long as oil guns in | ||||
service). | ||||
10 Isolate the vacuum line manual isolation valve provided corresponding to the CW pass which is to be isolated at | ||||
the condenser end (8.5m near LPBP). | ||||
11 Switch of the CW pass (which is to be isolated) inlet valve power supply, Then gradually close the inlet valve | ||||
manually from local and simultaneously observe the vacuum, CW discharge header pressure. After full closing, | ||||
Isolate the actuator power supply. | ||||
12 Switch of the CW pass (which is to be isolated) outlet valve power supply, Then gradually close the outlet valve | ||||
manually from local and simultaneously observe the vacuum, CW discharge header pressure. After full closing, | ||||
Isolate the actuator power supply. | ||||
13 Open the corresponding condenser water box vent valves (2nos) for depressurisation. | ||||
14 Open the drain valve provided in the corresponding water box for draining after depressurisation. | ||||
15 If draining of inlet water duct is started, then check sump level and put sump pumps in auto or start / stop | ||||
condenser pit sump pump for dewatering manually. | ||||
16 Further tighten inlet and outlet valves if there is any passing. | ||||
17 After isolation of CW pass, Gradually increase the load to approximately 350MW with 5 mills operation and | ||||
simultaneously monitor condenser vacuum. | ||||
18 Close TDBFP – A / B recirculation valve, which was kept opened previously after sufficient loading of both | ||||
TDBFPs. | ||||
19 Remove oil support after stabilisation of load at approximately 350MW with 5 mills operation. | ||||
20 Issue PFW after ensuring complete draining and proper isolation. | ||||
PROCEDURE FOR CW PASSES NORMALISATION: - | ||||
Revise the station DC as per the planned programme. | ||||
2 Ensure the cancellation of PFW and clearance from maintenance (TMD). | ||||
3 Ensure the complete box up of the CW pass. | ||||
4 Close the drain valve provided at the bottom of the corresponding water box. | ||||
5 Open the vent valves provided at the top of the corresponding water box. | ||||
6 Crack open the CW pass (which is isolated) inlet valve manually from local and observe the CW discharge header | ||||
pressure. | ||||
7 Ensure air is coming from the vent line and close it after ensuring complete venting. | ||||
8 Gradually full open the CW pass (which is isolated) inlet valve manually from local and observe the CW discharge | ||||
header pressure. | ||||
9 Gradually open the CW pass (which is isolated) outlet valve from local manually and observe the vacuum and CW | ||||
discharge header pressure. | ||||
10 Normalise the inlet and outlet valve actuator power supply | ||||
11 After full opening of CW pass inlet and outlet valves, Open the corresponding CW pass vacuum line manual | ||||
isolation valve at 8.5m near LPBP, which is isolated previously. | ||||
12 Take 6th mill into service and gradually increase the load to 450MW. | ||||
13 Adjust the MS pressure set point according to the variation of load. | ||||
14 Take 7th mill into service and increase the load to full (500MW). | ||||
15 Adjust the burner tilt to maintain M S & HRH temperature up to maximum possible (540C). | ||||
16 Take care of TDBFP – A /B recirculation control valve auto close protection. | ||||
17 Take care of ACW pump suction header pressure very low and discharge header pressure very high protection in | ||||
both corresponding units. | ||||
18 Put fuel master in auto. | ||||
19 Take corresponding CW pass OLTC into service. | ||||
20 Stop second vacuum pump and check vacuum. | ||||
21 Take unit control in to CMC mode. |
Thursday, May 10, 2018
CW PASS ISOLATION PROCEDURE:
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment