Seal Oil system Charging
Pre – start checks
(For
air side seal oil PPS)
-
Turbine lube oil system is in service.
-
Seal oil storage tanks level is normal ( low level alarm not persisting )
-
Ensure that following valves are open :----
- Shut off valve from seal oil storage tank at oil canal.
- Shut off valves before seal oil Pumps ( air side )
- Shut off valves after seal oil Pumps ( air side )
- Shut of valves before and after DPR valves
- Shut of valve before float valve in oil inlet to seal oil tank.
- Shut off valve after float valve in oil drain line from SOT
- Shut off valves after flow indicators of air side, H2 side and ring relief seal oil at 8.5 m rack.
- Air side and H2 side seal oil signal to pr. Equalizing valve at 8.5 m rack.
-
Ensure venting of air side seal oil cooler and filters.
-
Ensure cooling water is available for seal oil coolers.
-
Ensure root valves of all instruments are open at “O” m & 8.5 m
-
Ensure interconnecting valve to H2 side seal oil system is close.
-
Gen. Brg. Exhaust fan is in service.
-
By pass valve of float valve in oil drain line from SOT is close.
Pre
– start checks
(For
H2
side seal oil Pumps)
-
Air side seal oil circuit is in operation.
-
Air side seal oil pr. > 4.5 Ksc at 8.5 m.
-
Seal oil Tanks level is adequate.
-
Ensure that following valves are open
- H2 side seal oil Pump suction valve.
- H2 side seal oil Pump discharge value.
- Manual isolating value after DPR valve
- Isolating valve before H2 side seal oil cooler.
-
Ensure proper venting of H2 side seal oil coolers and filters.
-
Ensure cooling water is available for seal oil coolers.
-
Ensure that manual isolating valve in H2 side seal oil Pump discharge header for seal oil storage tank is close.
ROUTINE CHECKS FOR SEAL OIL SYSTEM
- Air side and H2 side seal oil pumps discharge pr. is ( 10 1) Ksc
-
Air side and H2 side seal oil temp in the range of 35 to 40C
-
Air side and H2 side seal oil filters are not chocked.
-
SOT level is normal
-
Inter connecting valve between H2 side and Air side seal oil circuits is close.Inter connecting valve in between DPR valves is close
- Stand-by pump is lined up and not rotating in reverse direction.
- Seal oil flow and pressure is adequate in air side, H2 side and ring relief supply line at 8.5 m rack.
- Air side seal oil / H2 gas differential pr. is 1.3 to 2 Ksc
- H2 side and air side seal oil DP at seals is 10-20 mbar.
- Gen. Brg. Vapour exhaust fan is running and ensure vapour is coming out to atmosphere.
- Ensure no oil in LLD ( Liquid Level Detector)
- By-pass valve of float in oil drain line from SOT is close.