Main Boiler Protection-Stage II 500 MW Rihand

Main Boiler Protection
  • Both ID fans off -            2 sec
  • Both FD fans off.
  • Emergency trip from OWS/ PB CCR PB Both 
  • RH protection             10 sec 
  • Water wall cir. Not adequate      5 sec        DP <10 psi) 
  • Furnace pr V high.     +150 mm WC
  • Furnace pr V low.       ‐175 mm WC
  • Drum level V high.      10 sec          + 250mm
  • Drum level V low.        15sec           ‐ 375mm
  • Low air flow <30%                       < 604T/Hr
  • All Boiler Feed pumps tripped.    10 sec
  • All SAPHs off.
  • Flame failure trip. 
  • Loss of all fuel trip 
  • Loss of 220 V DC          2 sec.
  • Less than FB &loss of 110 AC at any elevation in service 
  • Loss of 24V DC 